methodology

题目

methodology

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Risk management methodology should be adhered to in:

A construction projects

B system projects

C complex projects

D large projects

E All of the above.


正确答案:E

第2题:

192 Project management provides organizations with a methodology to:

A. Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure

B. Manage high risk repetitive work

C. Provide clients with multiple points of contact

D. Provide guidance in accomplishing repetitive activities

E. All of the above


正确答案:A

第3题:

Project management provides organizations with a methodology to:

ABecome more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure

BManage high risk repetitive work

CProvide clients with multiple points of contact

DProvide guidance in accomplishing repetitive activities

EAll of the above


正确答案:A
A

第4题:

()is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

A.PERT
B.AOA
C.WBS
D.PDM

答案:D
解析:
(73)用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称作节点)代表活动,它们之间用箭头连接,显示彼此之间存在的逻辑关系。A.PERT B. AOAC. WBS D. PDM

第5题:

Which of the following is not a part of reports?

A: catalogue

B: title

C: conclusion

D: methodology


正确答案: A

第6题:

_____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.

A Request for proposal

B Invitation to bid

C Request for quotation

D Intention for bid

E None of the above.


正确答案:A

第7题:

● Work authorization forms are needed in order to:

A Authorize line organizations to charge against the project

B Establish an audit trail

C Develop a structured methodology for release of funds

D All of the above

E A and C only


正确答案:D

第8题:

Work authorization forms are needed in order to:

AAuthorize line organizations to charge against the project

BEstablish an audit trail

CDevelop a structured methodology for release of funds

DAll of the above

EA and C only


正确答案:D
D

第9题:

● (75) Development is a structured design methodology that proceeds in a sequence from one phase to the next.

(75)

A. Waterfall

B. Phased

C. Prototyping

D. Parallel


正确答案:A

第10题:

Development is a structured design methodology that proceeds in a sequence from one phase to the next.

A.Waterfall
B.Phased
C.Prototyping
D.Parallel

答案:A
解析:
本题是考察开发模型概念。
瀑布模型(Waterfall)开发过程是通过设计一系列阶段顺序展开的,从系统需求分析开始直到产品发布和维护,每个阶段都会产生循环反馈。