A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()A、Upgrade system firmware to latest levelB、Upgrad

题目

A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()

  • A、Upgrade system firmware to latest level
  • B、Upgrade to AIX 5.3
  • C、Upgrade HMC to version 6.1
  • D、Convert rootvg filesystems to JFS2
参考答案和解析
正确答案:B
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

  • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
  • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
  • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
  • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

正确答案:D

第2题:

A Power Systems customer would like to upgrade their HMC to the latest version of software tosupport a new hardware feature. What resource will help identify dependencies for firmware and system software for their upgrade?()

  • A、ITSO Redbooks
  • B、Facts and Features
  • C、System Planning Tool
  • D、Fix Level Recommendation Tool

正确答案:D

第3题:

A System p administrator plans to install a new system with AIX 5.3 TL5 using a NIM server.  Which of the following provide post install diagnostics()

  • A、SPOT
  • B、lpp_source
  • C、mksysb
  • D、install CD

正确答案:A

第4题:

A production system needs to be upgraded from AIX V5.2 to AIX V5.3. All system logs and users need to be saved.  Which installation method will accomplish the upgrade()

  • A、Update Installation
  • B、Migration Installation
  • C、Preservation Installation
  • D、Mirror rootvg prior to a Preservation Installation

正确答案:B

第5题:

Prior to implementing an LPAR system, which of the following needs to be done?()

  • A、A graphics monitor must be attached to the server
  • B、Cluster System Management (CSM) software must be installed
  • C、The LPAR system must have an Hardware Management Console (HMC) connected
  • D、Each LPAR must be configured with a CDROM for operating system installation

正确答案:C

第6题:

A system administrator completed an upgrade of the maintenance level of their AIX system. Which of the following commands should be run to verify that the operating system is in a consistent state?()

  • A、instfix -i
  • B、lslpp -l
  • C、lppchk -v
  • D、oslevel -r

正确答案:C

第7题:

Company.com has ordered an 8-way p5-570 and plans to deploy four AIX 5L v5.3 LPARs. The pre-installation system design has all eight processors being placed in the shared processor pool, and four Micro-Partitions being assigned resources from the pool. Prior to the implementation of the system, the customer informs the technical specialist that one of the applications is only supported on AIX 5L 5.2. Which of the following changes to the system design should the technical specialist make to accommodate this change?()

  • A、Create all the partitions as AIX 5.2, each having two dedicated processors.
  • B、Purchase a system with two additional processors that can be assigned to the AIX 5.2 Partition.
  • C、Specify an AIX 5.2 partition using dedicated processors, reducing the number of processors in the shared pool.
  • D、Use the virtual I/O server to manage the disks and network connections removing the need for different levels of device drivers.

正确答案:C

第8题:

A system must be upgraded from AIX 5.1 to 5.2.  Which of the following scheduling processes should be performed? ()

  • A、 Schedule enough down time to backup, upgrade and reboot. 
  • B、 Backup, upgrade, then schedule enough down time to reboot the system. 
  • C、 Backup, then schedule enough down time to upgrade and reboot the system. 
  • D、 No scheduling processes are necessary because no down time is required.

正确答案:A

第9题:

A customer is planning to migrate a financial application to a 12-way p5-570 system with 96GB of memory.  The application data is stored on an ESS Model 800 attached to a p670 server with AIX 5.2.  They will have a short outage window to perform the data migration.  What is the quickest way to move all the data stored on the attached ESS from the p670 to the new p5-570?()

  • A、Use rsync to synchronize the data across servers.
  • B、Use exportvg and importvg to move the data to the target system.
  • C、Use NFS to copy the data from the source system to the target system.
  • D、Backup the data from the source system and restore to the target system.

正确答案:B

第10题:

A system administrator has just finished upgrading a system to AIX 5.2. If there are future problems, the system administrator would like to add an entry to the AIX errorlog to record this event. Which of the following commands can be issued for this purpose?()

  • A、/usr/bin/errmsg "System upgraded to AIX 5.2"
  • B、/usr/bin/errlog "System upgraded to AIX 5.2"
  • C、/usr/bin/errupdate "System upgraded to AIX 5.2"
  • D、/usr/bin/errlogger "System upgraded to AIX 5.2"

正确答案:D