GRANT dba TO dbmgr;
GRANT connect TO dbmgr;
GRANT resource TO dbmgr;
GRANT hs_admin_role TO dmbgr;
GRANT manage scheduler TO dbmgr;
第1题:
104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A. 1.10
B. 0.90
C. 0.956
D. 1.15
E. 0.869
第2题:
A. ENABLE启用
B. ENABLE_PROGRAM
C. VALIDATE_PROGRAM
D. SET_ATTRIBUTE设置属性
E. SET_ENABLED
第3题:
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A . 1.1
B . 0.9
C . 0.956
D . 1.15
E . 0.869
第4题:
Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()
第5题:
You notice that the elapsed time for an important database scheduler Job is unacceptably long.The job belongs to a scheduler job class and window.Which two actions would reduce the job‘s elapsed time?()
A. Increasing the priority of the job class to which the job belongs
B. Increasing the job‘s relative priority within the Job class to which it belongs
C. Increasing the resource allocation for the consumer group mapped to the scheduler job‘s job class within the plan mapped to the scheduler window
D. Moving the job to an existing higher priority scheduler window with the same schedule and duration
E. Increasing the value of the JOB_QUEUE_PROCESSES parameter
F. Increasing the priority of the scheduler window to which the job belongs
第6题:
A. SET_ATTRIBUTE_NULL
B. ALTER_JOB
C. ALTER_JOB_PARAMETERS
D. ALTER
E. SET_ATTRIBUTE
第7题:
A.Creating, dropping, and modifying tables and indexes
B.Initiating a binary backup of the database by using the START BACKUP command
C.Displaying replication status information
D.Shutting down the server by using the SHUTDOWN command
E.Creating and dropping databases
F.Creating and administering users
第8题:
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A . P
B . Q
C . R
D . S
E . T
第9题:
While creating a job class using the DBMS_SCHEDULER package, you set the logging level to LOGGING_RUNS. What would be the impact of this setting?()
第10题:
Which DBMS_SCHEDULER procedure(s) can be used to alter an existing job?()