Change to a 4-way p5-550
Use Capacity on Demand
Configure a fourth logical partition
Add memory to the configuration
第1题:
A customer has a requirement to eliminate single points of failure for an application. They have allocated one Ethernet adapter to each VIO server on the system. Which features of PowerVM and AIX will support the customer requirement?()
第2题:
Company.com has four pSeries servers in their data center and wants to deploy multiple Micro-Partitions. Which of the following data center servers can be used for this purpose?()
第3题:
Companycom is converting an application over to a p5 595 server with LPARs and has underestimated the processor requirements. The system has COD processors, but the customer does not know how to size the workload. What course of action would help identify the processor requirement?()
第4题:
Which functionality would a customer use to share available CPU resources between AIX and Linux partitions on a Power system?()
第5题:
Company.com wants to change the resource allocation for their AIX 5L V5.3 micro LPAR system. What is the smallest processor allocation than can be moved between partitions?()
第6题:
Company.com has ordered an 8-way p5-570 and plans to deploy four AIX 5L v5.3 LPARs. The pre-installation system design has all eight processors being placed in the shared processor pool, and four Micro-Partitions being assigned resources from the pool. Prior to the implementation of the system, the customer informs the technical specialist that one of the applications is only supported on AIX 5L 5.2. Which of the following changes to the system design should the technical specialist make to accommodate this change?()
第7题:
Company.com has a two-way p5-520 that will be running three shared processor Micro-Partitions consuming 60 percent of system resources. Immediately prior to shipment, the customer discovered they need to run a fourth server that requires AIX 5L V5.2. Which of the following will satisfy this requirement?()
第8题:
A customer has requested a proposal for a p5-520 with AIX 5.2 and Sysback. There are no plans to run LPARs or Micro-Partitions on the p5-520 in the near future. The customer has asked the pSeries technical specialist to recommend anything else that may be needed. Which of the following should be recommended in this situation?()
第9题:
Company.com has purchased a 2-way p5-520 and would like to create three Micro-Partitions on the server. Which feature of Advanced POWER Virtualization would allow them to create the desired number of partitions?()
第10题:
Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()