An administrator is configuring an LPAR for a NIM installati

题目
单选题
An administrator is configuring an LPAR for a NIM installation and is unsure if the 'Ping Test' option within SMS is a required configuration step. Which statement best describes the 'Ping Test' option?()
A

The 'Ping Test' is a recommended step to verify the IP information entered into the RIPL SMS panel.

B

The 'Ping Test' is a mandatory step required to commit the IP information entered into the RIPL SMS panel.

C

The 'Ping Test' is an optional step to verify network configuration entered into the RIPL SMS panel on older copper-based networks.

D

The 'Ping Test' is an optional step to verify network connectivity between client and server, where ICMP traffic is allowed on the connecting network.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV). Which of the following partitions has the minimum requirements to utilize virtual fibre channel?()

  • A、LPAR-A with 1Gb FC HBA and SAN connection
  • B、LPAR-B with 2Gb FC HBA and SAN connection
  • C、LPAR-C with 4Gb FC HBA and SAN connection
  • D、LPAR-D with 8Gb FC HBA and SAN connection

正确答案:B

第2题:

Which command should the administrator use to display the IPL progress/LED code of the partition?()

  • A、lsled -m System -r lpar 
  • B、lsrefcode -m System -r lpar 
  • C、lshwinfo -m System -r led_code 
  • D、lssyscfg -m System -r sys -F lpar_name,led_code

正确答案:B

第3题:

An administrator is creating a new LPAR with 6 virtual processors and 4 processing units. This LPAR must have the highest priority in the shared processor pool.  Which weight should be assigned to this LPAR?()

  • A、 0
  • B、 1
  • C、 255
  • D、 256

正确答案:C

第4题:

An administrator wants to deploy a complex LPAR environment on a 595. What is the most current tool available for documenting the proposed LPAR configuration and determining if there are adequate IO resources?()

  • A、LPAR Planning Tool.
  • B、System Planning Tool.
  • C、LPAR Validation Tool.
  • D、System Validation Tool.

正确答案:B

第5题:

A customer is in the process of testing their configuration prior to going live. The administrator discovers thatPowerHA is taking 31 seconds to deal with a standard NIC failure. What can the administrator do to speed upthe process of NIC failure detection and diagnosis?()

  • A、Tune the topsvcs NIM settings
  • B、Tune the grpsvcs NIM settings
  • C、Activate the fast failure detection (FFD) feature
  • D、Activate the Gigabit fast failover feature on the physical adapters

正确答案:A

第6题:

An administrator is configuring an LPAR for a NIM installation and is unsure if the 'Ping Test' option within SMS is a required configuration step. Which statement best describes the 'Ping Test' option?()

  • A、The 'Ping Test' is a recommended step to verify the IP information entered into the RIPL SMS panel.
  • B、The 'Ping Test' is a mandatory step required to commit the IP information entered into the RIPL SMS panel.
  • C、The 'Ping Test' is an optional step to verify network configuration entered into the RIPL SMS panel on older copper-based networks.
  • D、The 'Ping Test' is an optional step to verify network connectivity between client and server, where ICMP traffic is allowed on the connecting network.

正确答案:D

第7题:

An administrator wants to deploy a complex LPARenvironment on a 595. What is the most current tool available for documenting the proposed LPAR configuration and determining if there are adequate IO resources?()

  • A、LPAR Planning Tool.
  • B、System Planning Tool.
  • C、LPAR Validation Tool.
  • D、System Validation Tool.

正确答案:B

第8题:

An administrator has implemented the following LPARs on a Power 570 with 32 GB memory with 512 MB remaining for allocation: LPAR 1 memory : min = 10 GB des = 15 GB max = 24 GB  LPAR 2memory : min = 10 GB des = 15 GB max = 24 GB The administrator receives a request to add 2 GB to LPAR 1. The only way to do this is by moving memory from LPAR 2 to LPAR 1. The administrator attempts to move the memory, but the operation fails. The administrator can  however allocate 512 MB that is free to LPAR 1 on the 570.  What is the most likely cause of this failure when dynamically moving memory?()

  • A、 Maxperm% is set too low on LPAR 2
  • B、 Insufficient paging space on LPAR 1
  • C、 Service IBM.DRM is unavailable on LPAR 1
  • D、 Insufficient pinnable memory frames available on LPAR 2

正确答案:D

第9题:

An administrator is creating a new logical partition (LPAR) with 6 virtual processors and 4 processing units. This LPAR must have the highest priority in the shared processor pool. Which weight should be assigned to this LPAR?()

  • A、 0
  • B、 1
  • C、 255
  • D、 256

正确答案:C

第10题:

For NIM to install client machines located in a non-adjacent network, which routing must be defined?()  

  • A、Boot/install servers will be required on each intermediate network.
  • B、When an install is initiated by the client, routing is only required from the LPAR back to the NIM master.
  • C、When an install is initiated by the NIM master, routing is only required from the NIM master to the client.
  • D、Appropriate network NIM resources need to be defined to the NIM master to allow routing in both directions.

正确答案:D