75 A project manager trying to communicate accurately to the team should use:
A. the language of the team members
B. the language of the project manager
C. non-verbal methods
D. written memos
E. All of the above
第1题:
20.
A. causing
B. teaching
C. pretending
D. trying
第2题:
A. contact
B. connect
C. communication
D. communicate
第3题:
A、If…shall
B、Suppose…shall
C、Should…would
D、Had…should
第4题:
______ it rain tomorrow moring, the loading ______.
A.Should / will be postponed
B.If / shall be postponed
C.Should / would be postponed
D.If / has to be postponed
第5题:
对于场景:一个公司负责多个项目,每个项目(Project)由一个员工(Employee)团队( Team)来开发。下列UML概念图中,(41)最适合描述这一场景。
A.图A
B.图B
C.图C
D.图D
第6题:
A.understand
B.give
C.quote
D.communicate
第7题:
A、try
B、tried
C、tries
D、trying
第8题:
A.contact
B.talk
C.connect
D.communicate
第9题:
________ the vessel have no safety radiotelegraphy certificate at the time of her delivery,she ________ be held to be unseaworthy.
A.If/may
B.Will/shall
C.Should/would
D.Would/should
第10题:
已知基类Employee只有一个构造函数,其定义如下: Employee::Employee(int n):id(n){ } Manager是Employee的派生类,则下列对Manager的构造函数的定义中,正确的是?
A.Manager::Manager(int n):id(n){}
B.Manager::Manager(int n){id=n;}
C.Manager::Manager(int n):Employee(n){}
D.Manager::Manager(int n){Employee(n);}