一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()A、活动的总时差(float)B、只有最早开始(early start)与最晚开始时间(late Start)C、关键路径(critical path)D、A和C

题目

一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()

  • A、活动的总时差(float)
  • B、只有最早开始(early start)与最晚开始时间(late Start)
  • C、关键路径(critical path)
  • D、A和C
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Which of the following is indicative of negative float?

A The late start date is earlier than the early start date.

B The critical path supports the imposed end date.

C The early finish date is equal to the late finish date.

D When leads are employed in the schedule.

E The project is sinking.


正确答案:A

第2题:

一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()

A.活动的总时差(float)

B.只有最早开始(early start)与最晚开始时间(late Start)

C.关键路径(critical path)

D.A和C


参考答案:D

第3题:

Which of the following is indicative of negative float?

A.The late start date is earlier than the early start date.

B.The critical path supports the imposed end date.

C.The early finish date is equal to the late finish date.

D.When leads are employed in the schedule.

E.The project is sinking.


正确答案:A
A

第4题:

采用逆推法的目的在于决定()。

  • A、关键路径
  • B、最早开始和最早完成日期
  • C、最迟开始和最迟完成日期
  • D、赶工日期

正确答案:C

第5题:

在项目进度管理的方法中,顺推法用来定项目活动的哪些特征()

A.最早开始时间

B.最早结束时间

C.最晚开始时间

D.最晚结束时间


参考答案AB

第6题:

一旦制定出网络逻辑图,项目经理将会对网络进行顺推计算然后逆推计算。这样做将会提供关于的信息并且可确认()。

A.每项活动的时差,关键路线

B.每项活动的时差,高风险活动

C.人力短缺,高风险活动

D.高风险活动,非关键路线


参考答案:A

第7题:

计算出已完工网络的活动历时后,前推法和逆推法可以提供:

A、 活动浮动时间

B、 最早开始日期和最迟开始日期

C、 关键路径

D、 A和C


正确答案:D

第8题:

计算出已完工网络的活动历时后,前推法和逆推法可以提供:( )

A.活动浮动时间

B.最早开始日期和最迟开始日期

C.关键路径

D.A和C


正确答案:D

第9题:

逆推法计算项目网络活动时间决定()

A.活动最晚开始时间

B.活动最早结束时间

C.关键路径

D.A、C正确

E.A、B、C都正确


参考答案:D

第10题:

计算出已完工的活动历时后,顺推法和逆推法可以提供()。

  • A、活动浮动时间
  • B、最早开始日期和最迟开始日期
  • C、关键路径
  • D、活动浮动时间和关键路径

正确答案:D

更多相关问题