On some projects, especially ones of smaller scope, activity

题目
单选题
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
A

time estimating

B

cost estimating

C

project planning

D

schedule development

参考答案和解析
正确答案: D
解析: 该题的关键词为"activitysequencing. activity resourceestimating. Activityduration estimating",其语句结构为"activity sequencing, activity resource estimating, activity duration estimating, and (主语)are so tightly linked(谓语)",含义为"活动排序、活动资源估算、活动工期估算以及什么紧密相关",该题考察的知识点在于项目进度管理包含的各个子过程,依次为活动定义、活动排序、活动资源估算、活动工期估算、制定进度计划以及进度监控。考生在了解知识点的前提下能够轻松选出选项D,考生如果缺乏相应的知识,则只能碰运气了。
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

A.estimating

B.defining

C.planning

D.sequencing


参考答案:D

第2题:

If the aim of activity is to check that students can use the verbs correctly, you have to correct any major errors, especially those involving the verbs you have taught, or the activity will lose its point. ()

此题为判断题(对,错)。


参考答案:错误

第3题:

The "rolling wave" or "moving window" concept is used most frequently on projects where:

AThe baseline is frozen for the duration of the project and no scope changes are permitted

BMarketing is unsure of what the customer actually wants and reserves the right to make major scope changes

CThe low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work

DNetworking techniques are not appropriate

EAll of the above


正确答案:C

第4题:

● In multi-phase projects, the () Project process closes out the portion of the project scope and associated activities applicable to a given phase.()A.Scope B.Plan C.Close D.Control


正确答案:C
对于多阶段项目,项目收尾过程结束的是同给定阶段对应的部分项目范围和有关活动。

第5题:

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work


正确答案:D
解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

第6题:

● The "rolling wave" or "moving window" concept is used most frequently on projects where:

A The baseline is frozen for the duration of the project and no scope changes are permitted

B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes

C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work

D Networking techniques are not appropriate

E All of the above


正确答案:C

第7题:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development


正确答案:D

第8题:

Children are encouraged to put () some of their pocket money to buy Christmas presents for the poorer ones.

A、in

B、off

C、away

D、aside


参考答案:D

第9题:

● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.

(74)

A. milestone

B. baseline

C. quality

D. work


正确答案:D


 

 

第10题:

Based on the description of a lahar deposit, how do clasts and matrix particles differ in size?

A.Any clast is larger than the largest matrix particle.

B.Any clast is smaller than the smallest matrix particle.

C.Some, but not all, clasts are smaller than the largest matrix particle.

D.Some, but not all, matrix particles are larger than the smallest clast.


正确答案:A

更多相关问题