单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical spec

题目
单选题
The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
A

Use eConfig to configure and validate each pSeries and p5 system.

B

Engage Advanced Technical Support to review any outstanding technical issues.

C

Confirm with the customer that the solution design meets their requirements.

D

Perform a Pre-Install Solution Assurance Review to validate required power requirements.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Upon announcement,the specific details surrounding the Virtual I/O Server requirements and performance are still being defined.  The customer has engaged IBM to provide a server consolidation solution and would like to take advantage of the VIO Server benefits. How should the pSeries technical specialist best address this?()

  • A、Design the solution and present it confidently so the customer does not question it.
  • B、Design the solution and ensure the customer understands the unknowns with the new technology.
  • C、Explain to the customer that the VIO Server does not benefit them when doing server consolidation so it has not been configured.
  • D、Explain to the customer that the details surrounding the VIO Server have not been clearly defined so designing a solution is premature.

正确答案:B

第2题:

A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology.  Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()

  • A、p690 with Dynamic LPAR
  • B、Grid of SP switch-attached p5-550s
  • C、p690 with Advanced POWER Virtualization
  • D、p5-570 with Advanced POWER Virtualization

正确答案:D

第3题:

A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements written from the perspective of user and focus on user needs are called( ). Requirements written from the developer&39;s perspective and describe how the system will be implemented are called( ). Requirements evolve from detailed statemens of business capabilities that a system should have to detailed statements of the technical way in which the capabilities will be implemented in the new system. Requirements can be either functional or nofunctional in nature. For example, during the analysis phase of travel vehicles sales system, the system that must have the ability to search for available inventory is( ). The requirement that the system should be able to work on any Web browser belongs to( ). That customer personal information is protected in compliance with the Data Protection Act is a requirement of( ).

A.operational requirements B.business requirements C.technical requirements D.system requirements A.operational requirements B.business requirements C.technical requirements D.system requirements A.a functional requirements B.a technical requirements C.an operational requirements D.a service requirements A.functional requirements B.technical requirements C.operational requirements D.information requirements A.system constraint B.system performance C.secrity and control D.cultural and political


正确答案:B,D,A,C,D

第4题:

When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()

  • A、xSeries specialist,as the customer may have some Intel-based systems.
  • B、Hardware customer engineer,as they will be installing the entire solution.
  • C、Services specialist,as they can provide education recommendations for the entire solution. 
  • D、Storage specialist,as the customer may need disk to store the data and tape to backup the data.

正确答案:D

第5题:

After putting together a configuration that meets customer’s requirements, a TDA is suggested. The customer is not familiar with the TDA process and asks why this should be done. This of the following is the benefit of TDA?()

  • A、 A TDA are recommended only for high end hardware and very large or complex business opportunities
  • B、 A TDA will ensure the solution and configuration are complete and technically sound and meet customer requirements
  • C、 A TDA will guarantee that the hardware will work in customer’s environment at the volumes projected
  • D、 A TDA brings an IBM technician onsite to properly inspect and installed hardware and related software

正确答案:B

第6题:

A sales specialist is presented with a very large, complex opportunity. The customer is in the process of identifying business requirements.  Which of the following tasks is most important to position IBM as the leader to capture this opportunity?()

  • A、Call the IBM Client Representative and ask the rep to influence the company’s executives.
  • B、Develop a strategy to better understand and possibly influence the customer’s success criteria.
  • C、Using IBM’s opportunity management system, request a technical team be formed to design a solution.
  • D、Nominate the customer for a funded IBM Server Consolidation study.

正确答案:B

第7题:

A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()

  • A、Design the least-cost solution to prevent the competition from winning the business.
  • B、Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.
  • C、Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.
  • D、Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

正确答案:D

第8题:

A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements written from the perspective of user and focus on user needs are called __(71)__. Requirements written from the developer's perspective and describe how the system will be implemented are called __(72)__. Requirements evolve from detailed statemens of business capabilities that a system should have to detailed statements of the technical way in whick the capabilities will be implemented in the new system. Requirements can be either functional or nofunctional in nature. For example, during the analysis phase of travel vehicles sales system, the system that must have the ability to search for available inventory is __(73)__. The requirement that the system should be able to work on any Web browser belongs to __(74)__. That customer personal information is protected in compliance with the Data Protection Act is a requirement of __(75)__.
(72)应选?

A.operational requirements
B.business requirements
C.technical requirements
D.system requirements

答案:D
解析:
需求仅仅是系统必须做什么或者需要具备哪些特性的陈述。从用户的角度编写的需求和关注用户需求的需求称为(71)。从开发人员的角度编写的需求描述系统将如何实现被称为(72)。要求从具体的业务能力状态演化而来,系统应该具备详细的技术方式陈述,以便在新系统中实现能力。要求可以是功能性的,也可以是非功能性的。例如,在旅行车销售系统的分析阶段,必须具备搜索可用库存能力的系统是(73)。系统应能够在任何Web浏览器上工作的要求属于(74)。客户的个人信息受到“数据保护法”的保护是(75)的要求。

(72) A.操作需求 B.业务需求

C.技术需求 D.系统需求

第9题:

A solution provider has proposed a pSeries solution to a new customer.  The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation.  The solution provider has not been able to get a clear understanding as to how the customer will backup the system.  What would be the most appropriate action to address the risks with this solution?()

  • A、Sell Sysback
  • B、Conduct a SAR
  • C、Sell Supportline
  • D、Provide a project timeline

正确答案:B

第10题:

The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()

  • A、Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570
  • B、Designed a p670 because it supports AIX 5.1 partitions
  • C、Initially designed a solution supporting AIX 5.1 partitions
  • D、Gained customer approval for the final design prior to ordering the system

正确答案:D

更多相关问题