单选题A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server. Which action will reduce the potentia

题目
单选题
A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server. Which action will reduce the potential vendor software costs?()
A

Create capped partitions for the database servers.

B

Create workload partitions for the database servers.

C

Create a separate shared processor pool for the database servers.

D

Create virtual processors equal to the entitlement for database servers.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer is running system management software on one of their Windows xSeries servers, and the software seems to slow down their database application over time.  The customer is running IBM Director in their environment.  Which IBM Director tool can they utilize to guarantee processor time for the different applications and optimize the server performance?()

  • A、Software Rejuvenation
  • B、Capacity Manager
  • C、Capacity Workload Manager
  • D、Aurema Application Workload Manager

正确答案:D

第2题:

A customer has two Power 770 systems with 4 enclosures each.  Thirty two cores and 1TB of memory are activated on each system.  Each system has 3 database partitions and each partition has 10 cores and 300GB of memory.   Which solution will provide automated recovery of unplanned outages at least cost?()

  • A、Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failure
  • B、Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occurs
  • C、Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHA
  • D、Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover

正确答案:B

第3题:

A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server. Which action will reduce the potential vendor software costs?()

  • A、Create capped partitions for the database servers.
  • B、Create workload partitions for the database servers.
  • C、Create a separate shared processor pool for the database servers.
  • D、Create virtual processors equal to the entitlement for database servers.

正确答案:C

第4题:

In which two environments would intra-partition parallelism be used? ()

  • A、Single database partition, single processor  
  • B、Single database partition, multiple processors  
  • C、Multiple database partitions, single processor  
  • D、Multiple database partitions, multiple processors

正确答案:B,D

第5题:

A database administrator wants to design a multi-partition database that can take advantage of both intra-partition parallelism and inter-partition parallelism. Which configuration will allow the use of these types of parallelism while using the least number of hardware components (servers, processors)? ()

  • A、one server having at least two processors  
  • B、two servers having one processor and one logical database partition  
  • C、one server having four processors and two logical database partitions  
  • D、two servers each having four processors and two logical database partitions

正确答案:C

第6题:

A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()

  • A、Build the logical partition infrastructure based on 6 or more VLANs.
  • B、Build the logical partition infrastructure based on two or more IVEs.
  • C、Build the logical partition infrastructure based on Partition Mobility.
  • D、Build the logical partition infrastructure based on redundant VIO Servers.

正确答案:D

第7题:

A company needs additional storage for a block I/O based database application. The application has low I/O bandwidth requirements across the campus. The customer has a TCP/IP infrastructure and is interested in low-cost products that are compatible with its environment. Which technology is most appropriate for this customer?()

  • A、SAN
  • B、FCoE
  • C、FCIP
  • D、iSCSI

正确答案:D

第8题:

A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()

  • A、 PowerVM Lx86
  • B、 PowerVM Express Edition
  • C、 PowerVM Standard Edition
  • D、 PowerVM Enterprise Edition

正确答案:C

第9题:

A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?()

  • A、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be capped.
  • B、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be uncapped.
  • C、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partitions to use no more than one core. Configure the HMC scheduler to  dynamically assign processors among the pools over a day.
  • D、Create a shared processor pool for each production partition, with the maximum processor limit set to the  licensing limit for the application in the pool. Assign the development and testing partitions to a processor  pool with a maximum of 1 core. Configure each partition to use uncapped processing.

正确答案:D

第10题:

A customer has a database application that is accessed by a large number of people through a web interface from multiple remote locations.  Which of the following questions will provide the information necessary to design the best performing storage solution?()

  • A、How many web servers will be connected to the database?
  • B、Will the database be run on a Windows solution?
  • C、How many concurrent users will be accessing the database?
  • D、What are the types of transactions run against the database?

正确答案:D