第1题:
Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?
A . Matrix
B . Pure project
C . Project coordinator
D . Project expediter
E . Classical/traditional
第2题:
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第3题:
The scope of a project can be expected to change if:
A.The project manager must provide cost estimates without having a design concept
B.Oversimplification (underestimating) of the nature of the work occurs
C.The project manager is assigned after the project is defined, and the cost and schedule are approved
D.A clear objective is not provided
E.All of the above are possible based upon the situation
第4题:
● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .
(73) A. change the scope baseline
B. contact the customer to determine if the change adds value
C. call a meeting of the change control board
D. change the project' s objectives
第5题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第6题:
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A. Change the scope baseline
B. Prepare a variance report
C. Call a meeting of the configuration control board
D. Change the project's objectives
E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第7题:
● The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
第8题:
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
第9题:
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第10题:
●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).
(75) A. technical specifications
B. performance specifications
C. product descriptions
D. quality assurance