The inputs of developing project management plan do not include()

题目
The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.

B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.

C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


参考答案:C
沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D:沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

第2题:

● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

(75)

A. Project Scope Statement

B. Project Management Plan

C. Forecasts

D. Project Charter


正确答案:B

试题(75)分析
  项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
  A.项目范围说明书                    B.项目管理计划
  C.项目预测                          D.项目章程
参考答案
  (75)B

第3题:

The following individuals are responsible for determining the content of the Communications Management Plan.

A Project Sponsor

B Task Manager(s)

C Director of Communications

D Project Manager


正确答案:D

第4题:

The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


正确答案:B
项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

第5题:

The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


正确答案:B
制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

第6题:

● The inputs of developing project management plan do not include (72).

(72)

A. project charter

B. stakeholder management strategy

C. project scope statement

D. outputs from planning processes


正确答案:B

第7题:

The inputs of developing project management plan do not include (72) .

A.project charter

B.stakeholder management strategy

C.project scope statement

D.outputs from planning processes


正确答案:B

第8题:

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A.Project

B.project management team

C.performingorganization

D.customer


参考答案:C

该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

第9题:

The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


正确答案:B
制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

第10题:

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

A.Developing project charter

B.Developing project management plan

C.Analyzing project risks

D.Monitoring and controlling project


正确答案:C

更多相关问题