An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()

  • A、The administrator will need to perform an rg_move operation
  • B、The administrator will need to un-manage and re-manage the resource group
  • C、The administrator will need to execute the new start script from the command line
  • D、The new start script will be executed as part of the DARE operation to synchronize the cluster