A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?()
第1题:
Companycom has a 16 way 1.65 GHz p5 590 and wants to install a i5/OS partition on their server. The customer wants to keep installation costs to a minimum by sharing devices between all LPARs. Before the operating system can be installed in this partition, the customer was told that there are certain limitations that must be observed. What are these limitations?()
第2题:
A storage specialist is discussing the customer’s high availability plan and discovers that they areonly 80 kilometers (50 miles) from the intended site. They require 7 x 24 x 365 data availability in aUNIX environment with an RPO of two minutes. They have two DS5300 systems located at bothsites. Which of the following IBM storage functions best meets the customer’s businesscontinuance requirements?()
第3题:
During the implement phase, systems acceptance testing provides which two of the following services for the customer()
第4题:
A database administrator wants to design a multi-partition database that can take advantage of both intra-partition parallelism and inter-partition parallelism. Which configuration will allow the use of these types of parallelism while using the least number of hardware components (servers, processors)? ()
第5题:
A small IT department is deploying Power 720 servers exploiting virtualization technologies. Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()
第6题:
A customer needs a new 4-way p630 with three partitions to support three AIX 5.2 applications. Each partition requires two of the following: OS boot drives, fiber adapters, and gigabit Ethernet adapters. The customer has an HMC with an available serial port. In addition to the model 6C4, which of the following is required to meet the customer’s requirements?()
第7题:
A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()
第8题:
A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows. Which of the following design consideration statements is correct?()
第9题:
A customer has two Power 770 systems with 4 enclosures each. Thirty two cores and 1TB of memory are activated on each system. Each system has 3 database partitions and each partition has 10 cores and 300GB of memory. Which solution will provide automated recovery of unplanned outages at least cost?()
第10题:
Companycom is planning to do server consolidation on POWER5. The customer has a test environment, a QA environment and a production environment for two applications. Both the test and QA environments are very small and are only utilized when new releases are being developed and tested. They require less than 1 CPU each. Both production applications require 2 CPUs for day-to-day operation and can require up to an additional 2 CPUs each during abrupt peak requirements. What is the best design for the LPARs?()