Having been familiar with his ability, ().
第1题:
In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A . Not working directly with the assigned functional employees
B . Employees spend only a short amount of time assigned to the project
C . Not being knowledgeable enough to evaluate employees on technical judgment
D . All of the above
E . A and B only
第2题:
22 In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A. Not working directly with the assigned functional employees
B. Employees spend only a short amount of time assigned to the project
C. Not being knowledgeable enough to evaluate employees on technical judgment
D. All of the above
E. A and B only
第3题:
The scope of a project can be expected to change if:
A.The project manager must provide cost estimates without having a design concept
B.Oversimplification (underestimating) of the nature of the work occurs
C.The project manager is assigned after the project is defined, and the cost and schedule are approved
D.A clear objective is not provided
E.All of the above are possible based upon the situation
第4题:
● A Gantt chart is useful in determining:
A the level of effort for a task
B when a task starts and stops
C how tasks are related to each other
D who is assigned to do a task
E All of the above.
第5题:
123 The scope of a project can be expected to change if:
A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs
C. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not provided
E. All of the above are possible based upon the situation
第6题:
20 A Gantt chart is useful in determining:
A. the level of effort for a task
B when a task starts and stops
C. how tasks are related to each other
D. who is assigned to do a task
E. All of the above
第7题:
41 The scope of a project can be expected to change if:
A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs
C. The project manager is assigned after the project is defined, and the cost and schedule are approved
D. A clear objective is not provided
E. All of the above are possible based upon the situation
第8题:
A Gantt chart is useful in determining:
A.the level of effort for a task
B.when a task starts and stops
C.how tasks are related to each other
D.who is assigned to do a task
E.All of the above.
第9题:
● The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
第10题:
此题为判断题(对,错)。