翻译:All Risks()

题目

翻译:All Risks()

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Many companies self insure against some risk. Problems which can arise from self-insurance include:

A failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company

B stiff competition from insurance companies

C confusion of business risks with insurable risks.

D A and C

E All of the above.


正确答案:D

第2题:

Since risk is associated with most projects, the best course of action is to:

A cover all project risks by buying appropriate insurance

B ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C avoid projects with clear and present risks

D eliminate all known risks prior to the execution phase of the project

E identify various risks and implement actions to mitigate their potential impact


正确答案:E

第3题:

Risks include the following types:

A Business risk

B pure risk

C Insurable risk

D A and B

E All of the above.


正确答案:E

第4题:

163 Many companies self insure against some risk. Problems which can arise from self-insurance include:

A. failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company

B. stiff competition from insurance companies

C. confusion of business risks with insurable risks.

D. A and C

E. All of the above


正确答案:D

第5题:

77 Since risk is associated with most projects, the best course of action is to:

A. cover all project risks by buying appropriate insurance

B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C. avoid projects with clear and present risks

D. eliminate all known risks prior to the execution phase of the project

E. identify various risks and implement actions to mitigate their potential impact


正确答案:E

第6题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第7题:

Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:

A Buyer

B Third party

C Contractor

D All of the above

E None of the above


正确答案:C

第8题:

Risk mitigation includes all but which of the following:

A Developing system (policies, procedures, responsibilities)

B Obtaining insurance against loss

C performing contingent planning

D developing planning alternatives

E identification of project risks.


正确答案:E

第9题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第10题:

15 Risks include the following types:

A. Business risk

B. pure risk

C. Insurable risk

D. A and B

E. All of the above


正确答案:E

更多相关问题