You are working on the cost budget for one project. Which of

题目
单选题
You are working on the cost budget for one project. Which of the following is true()
A

This process assigns cost estimates to project activities including risks and contingency plans.

B

The cost baseline will be used to measure variances and future project performance.

C

This process assigns cost estimates for expected future period operating costs.

D

The cost baseline is the expected cost for the project.

参考答案和解析
正确答案: C
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

65 Which of the following is referred to as sunk cost:

A. management reserve

B. contingency fund

C. cost budgeted for construction under water

D. expended funds over which there is no further control

E. forecasted budget over-runs


正确答案:D

第2题:

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.

B.The cost baseline will be used to measure variances and future project performance.

C.This process assigns cost estimates for expected future period operating costs.

D.The cost baseline is the expected cost for the project.


参考答案:B

第3题:

The Cost Performance Index is computed as:

A . budget cost of work performed divided by actual cost of work performed

B . budget cost of work performed minus actual cost of work performed

C . budget cost of work performed minus budget cost of work scheduled

D . budget cost of work scheduled divided by budget cost of work performed

E . actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第4题:

( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

A.The control accounts

B.Funding requirement

C.The cost estimates

D.The cost baseline


正确答案:D

第5题:

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided


正确答案:B
你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万工程款,完成了预算中28万的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____________。

第6题:

114 The Cost Performance Index is computed as:

A. budget cost of work performed divided by actual cost of work performed

B. budget cost of work performed minus actual cost of work performed

C. budget cost of work performed minus budget cost of work scheduled

D. budget cost of work scheduled divided by budget cost of work performed

E. actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第7题:

● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

(74)

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided


正确答案:B

第8题:

Which of the following is referred to as sunk cost:

A . management reserve

B . contingency fund

C . cost budgeted for construction under water

D . expended funds over which there is no further control

E . forecasted budget over-runs


正确答案:D

第9题:

Why are you working in a field other than the one in which you have a degree?


正确答案:
          

第10题:

You are working on the cost budget for one project. Which of the following is true()

  • A、This process assigns cost estimates to project activities including risks and contingency plans.
  • B、The cost baseline will be used to measure variances and future project performance.
  • C、This process assigns cost estimates for expected future period operating costs.
  • D、The cost baseline is the expected cost for the project.

正确答案:B

更多相关问题