第1题:
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A. Change the scope baseline
B. Prepare a variance report
C. Call a meeting of the configuration control board
D. Change the project's objectives
E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第2题:
our writing in the g time. After that, we have to check our 79.
第3题:
During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B.Is still the original baseline but annotated to reflect that a change has taken place.
C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E.Is the same since baseline schedules cannot change once the development phase is completed.
第4题:
All the damage and shortage,______ those incurred after discharge and before delivery to receivers,should be noted in the discharging report.
A.Including
B.Besides
C.Except
D.In addition to
第5题:
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第6题:
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第7题:
有如下程序; Private SubForm_Click() Dim check As Boolean,n As Integer check=False n=0 Do Do While n<10 n=n+1 If n=5 Then check=True Exit Do End if Print n; Loop Loop Until check = True End Sub 程序运行后,输出的结果是 ______ 。
A.1 2 3
B.1 2 3 4
C.1 2 3 4 5
D.1 2 3 4 5 6
第8题:
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.
C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E. Is the same since baseline schedules cannot change once the development phase is completed
第9题:
A. Logical network diagram
B. History logs
C. Baseline configurations
D. Wiring schematics