After a baseline check was completed it was noted that the n

题目
单选题
After a baseline check was completed it was noted that the network was working far below the level of the last baseline. Which of the following should the technician do NEXT to determine where the network problems are occurring?()
A

Upgrade the firmware on all routers and switches

B

Reboot the entire network one device at a time

C

Conduct a network traffic analysis

D

Rerun the baseline to ensure the results were correct

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第2题:

our writing in the g time. After that, we have to check our 79.


正确答案:
79. given

第3题:

During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.

B.Is still the original baseline but annotated to reflect that a change has taken place.

C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

E.Is the same since baseline schedules cannot change once the development phase is completed.


正确答案:C

 

第4题:

All the damage and shortage,______ those incurred after discharge and before delivery to receivers,should be noted in the discharging report.

A.Including

B.Besides

C.Except

D.In addition to


正确答案:A

第5题:

A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:D
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
  选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
  由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。

第6题:

● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A Change the scope baseline

B Prepare a variance report

C Call a meeting of the configuration control board

D Change the project's objectives

E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第7题:

有如下程序; Private SubForm_Click() Dim check As Boolean,n As Integer check=False n=0 Do Do While n<10 n=n+1 If n=5 Then check=True Exit Do End if Print n; Loop Loop Until check = True End Sub 程序运行后,输出的结果是 ______ 。

A.1 2 3

B.1 2 3 4

C.1 2 3 4 5

D.1 2 3 4 5 6


正确答案:B
解析:本题给出的程序由两层循环组成,外层循环使用的语句是Do...Until,内层循环使用的语句是Do While。Print语句在内层循环的End if语句的下面,内层循环共循环了4次,Print语句输出的值分别为1、2、 3、4;当内层循环到第5次时,将标志值check设置为True,并用Exit Do语句强制退出内层循环。外层循环则在检测到标志值check为True时,立即退出循环,而不会打印输出5。

第8题:

156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.

C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

E. Is the same since baseline schedules cannot change once the development phase is completed


正确答案:C

第9题:

An administrator has completed the installation of a new WLAN. Which of the following configuration management documents needs to be updated?()

A. Logical network diagram

B. History logs

C. Baseline configurations

D. Wiring schematics


参考答案:A

第10题:

After riveting is completed, the joints on the shell of a vessel are generally made watertight by________.

A.faying

B.caulking

C.felt or canvas packing

D.red lead


正确答案:B
铆接完成后,连接船壳通常使用捻缝使其水密。

更多相关问题