An administrator has a two-node PowerHA cluster in a mutual 

题目
单选题
An administrator has a two-node PowerHA cluster in a mutual takeover configuration. He needs to updatefrom 5.5 service pack 1 to 5.5 service pack 2. Which of the following actions will perform the updates with norisk of disruption to applications running in the cluster?()
A

Unmanage resource groups on all nodes, update the cluster filesets, start cluster services on all nodes,ensure cluster services stabilize

B

Update the cluster filesets on all nodes. Run ’refresh -s clstrmgrES’ on one node, wait for the cluster tostabilize, repeat for all other nodes

C

Unmanage resource groups on one node, update the cluster filesets, start cluster services. Wait for thecluster to stabilize and repeat for all other nodes.

D

Bring resource groups (RGs) online on all nodes concurrently, bring RGs offline on one node, update thecluster filesets, bring RGs online, repeat for all other nodes

参考答案和解析
正确答案: C
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

An administrator has added an additional network adapter to each cluster node. The adapters  have been configured and tested, and the /etc/hosts file has been updated. However,the adapters do not appear in the pick list when the administrator tries to define the adapters to HACMP.  What would be required to correct this problem?()  

  • A、 Rerun autodiscovery.
  • B、 Synchronize the cluster.
  • C、 Restart cluster services.
  • D、 Delete and recreate the adapters.

正确答案:A

第2题:

An administrator is configuring a new cluster and has a requirement for a notification to be generated if the /tmp File System becomes greater than 90% full. Which of the following PowerHA components will support theadministrator’s requirement?()

  • A、Pre-defined Events
  • B、User-defined Events
  • C、Remote notification methods
  • D、The integration between RMC and WebSM

正确答案:B

第3题:

A client wants to implement a highly available cluster between two sites. At each site the client has an IBMDS8300. At each site, the client would like a single node which will be connected through a SAN to the local DS8300but not the remote DS8300. Which clustering product could be used to provide high availability for this infrastructure?()

  • A、PowerHA/XD for GLVM
  • B、PowerHA with cross-site LVM
  • C、PowerHA/XD for Metro Mirror
  • D、PowerHA/XD for Global Mirror

正确答案:A

第4题:

An architect is configuring a PowerHA cluster in the following way:The cluster will consist of two nodes. Each node will have two boot interfaces configured as a single PowerHA network. The cluster is to have asingle resource group with a single service address.Heartbeating over aliased is not to be used. What is the minimum number of subnets required to implement this cluster?()

  • A、1
  • B、2
  • C、3
  • D、4

正确答案:C

第5题:

A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()  

  • A、 The resource group DNP has been configured.
  • B、 The resource group option CWOF has been enabled.
  • C、 The resource group option Inactive Takeover is set.
  • D、 A resource group fallback timer has been configured.

正确答案:B

第6题:

An administrator wants to install Web SMIT on a node that is not part of a cluster. Which PowerHA filesetprovides this function?()

  • A、cluster.sysmgt.wsm
  • B、cluster.es.client.wsm
  • C、cluster.es.server.websm
  • D、cluster.sysmgt.websm.rte

正确答案:B

第7题:

An administrator has a 2 node cluster running PowerHA version 5.5. They remove a resource group from theactive cluster configuration. When performing a verify and synchronize of the cluster, the administrator getsthe following error: "migcheck[471]: cl_connect() error, nodename=Node1, rc=-1 cldare: A communication error prevents obtaining the VRMF from remote nodes. A DARE event cannot be run until this is corrected. Please ensureclcomd is running." What is the most likely cause of this error?()

  • A、There is a DARE lock in place
  • B、A PowerHA migration is in progress
  • C、Cluster services is not active on the other node
  • D、The other cluster node is running a different version of RSCT

正确答案:C

第8题:

An administrator is installing PowerHA filesets, and this cluster will be cross-mounting filesystems using NFSversion 4. Which additional fileset is required?()

  • A、bos.net.tcp.client
  • B、cluster.es.nfs.rte
  • C、bos.nfsv4.server.rte
  • D、cluster.es.nfs.server

正确答案:B

第9题:

An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()

  • A、Use the clstat command and verify the cluster is in a stable state
  • B、After each node is upgraded, run a verification and synchronization
  • C、After all nodes are upgraded, run a verification and synchronization
  • D、Take a snapshot of each node and verify the configuration is the same

正确答案:C

第10题:

An administrator is planning for a six node cluster but is concerned about the administration needed tomanage user accounts throughout the cluster. What PowerHA feature could the administrator use to reducethe administration overhead?()

  • A、LDAP Authentication Module
  • B、Smart Assist for Active Directory
  • C、C-SPOC for user and password management
  • D、File Collections designating one node as the primary authentication node

正确答案:C

更多相关问题