第1题:
For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?
A project office memo
B project office directive
C project team meeting
D formal report
E counseling sessions
第2题:
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
第3题:
A proven effective means to insure quality conformance is to:
A . delegate accountability to subordinates
B . revise quality specifications to match quality measurements
C . train workers in proper quality methods
D . inspect quality into the product
E . make quality a higher priority than cost or schedule
第4题:
The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out
第5题:
●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.
(71)A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstorming
第6题:
100 The auditing function that provides feedback about the quality of output is referred to as:
A. quality control.
B. quality planning.
C. quality assurance.
D. quality improvement
E. All of the above
第7题:
The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.
A.Manage quality
B.Quality audit
C.Quality metrics
D.Quality improvement
第8题:
The auditing function that provides feedback about the quality of output is referred to as:
A . quality control.
B . quality planning.
C . quality assurance.
D . quality improvement
E . All of the above.
第9题:
is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
第10题:
Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥