Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()
A

POWER5 runs in an SMP mode as default

B

POWER5 can run in a full system mode the same as the p690

C

POWER5 can run in full system mode with the purchase of PLM

D

POWER5 can run in a full system mode, but it is in LPAR mode

参考答案和解析
正确答案: A
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer has just received three enterprise systems that support a total of 48 LPARs. Which installation method expedite the process?()

A.Network installation manager

B.Boot from installation media

C.A migration install

D.Copy the system using the HMC


参考答案:A

第2题:

Today is Jenny’s wedding day.She_______to Thomas.

A.just has got married
B.has just married
C.was just married
D.has just got married

答案:D
解析:

第3题:

Unluckily, when I dropped in , Dr. Smith (), so we only had time for a few words.

A、just left

B、was just leaving

C、has just left

D、had just left


参考答案:B

第4题:

Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()

  • A、POWER5 runs in an SMP mode as default
  • B、POWER5 can run in a full system mode the same as the p690
  • C、POWER5 can run in full system mode with the purchase of PLM
  • D、POWER5 can run in a full system mode, but it is in LPAR mode

正确答案:D

第5题:

The pSeries technical specialist has a number of tasks to perform and does not have time to do them all.  It is a week before the end of quarter and the account executives all state that their individual requests are the highest priority.  How should the following task list be prioritized? () 1. Return a call from customer seeking compatibility information.  2. Configure three p690 servers to be ordered in two weeks.  3. Prepare a POWER5 presentation to give to a customer in two weeks.  4. Configure three p690 servers to be ordered this quarter.

  • A、4,2,1,3
  • B、4,3,1,2
  • C、2,4,3,1
  • D、2,3,4,1

正确答案:A

第6题:

A large sum of money has been allocated ated for buying new books for the library.

A:assigned
B:persuaded
C:asked
D:ordered

答案:A
解析:
本句意思:一大笔款项被拨给了图书馆来购买新书。allocate意思是“分配,分派,把……拨给”,与assign(分配,选派)意思相近。persuade说服,劝说;ask要求,询问;order命令,订购。

第7题:

Companycom has been performing scheduled backups of their data to tape using "tar" in a script for over one year with no problems. Recently, the tar command is returning a non zero return code during the backup phase, causing the script to fail. What is the primary cause of this problem?()

  • A、The files have grown to over eight gigabytes in size
  • B、The file systems are corrupt, and fsck should be run
  • C、The tape block size has been changed from the default
  • D、The user’s limit has been changed to less than eight gigabytes

正确答案:A

第8题:

You would like to view all Fast Ethernet interfaces currently using VLAN tagging and the specific VLANs each interface is using.Which CLI command displays this information?()

A.A

B.B

C.C

D.D


参考答案:C

第9题:

Companycom has just added some new disk drives to a p5 590. The customer needs to know the largest Logical Track Group that these drives will support. What is the best way to locate this information?()

  • A、Use lquerypv to read the drive
  • B、Use lspv and look at PP Size value
  • C、Look on the outside of the drive itself
  • D、Use bootinfo to find the LTG on the drive

正确答案:A

第10题:

A solution for two batch applications was proposed in Companycom meeting. They are currently running in two LPARs on a p690. On a daily basis, both applications use 15% of the machine for their workload, and increase to 100% when their weekly reports are run. Since the reports are not run on the same day, what is the best solution?()

  • A、COD
  • B、DLPAR
  • C、One big LPAR
  • D、Two separate p690 machines

正确答案:B