What is the key objective of the plan phase?()

题目
单选题
What is the key objective of the plan phase?()
A

Identify the activities involved in installing and configuring equipment at a customer’s site or sites

B

Describe the day-to-day activities required to support, manage, and monitor a newly implemented system

C

Access current network readiness, site readiness, and operational readiness in preparation for designing a solution proposal

D

Gain an understanding of high-level business and technical requirements

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Consider the query:Mysql> SET @run = 15;Mysql> EXPLAIN SELECT objective, stage, COUNT (stage)FROM iteminformationWHERE run=@run AND objective=’7.1’GROUP BY objective,stageORDER BY stage;The iteminformation table has the following indexes;Mysql> SHOW INDEXES FROM iteminformation:This query is run several times in an application with different values in the WHERE clause in a growing data set.What is the primary improvement that can be made for this scenario?()

A.Do not pass a user variable in the WHERE clause because it limits the ability of the optimizer to use indexes

B.Add an index on the objective column so that is can be used in both the WHERE and GROUP BY operations

C.Drop the run_2 index because it has caused a conflict in the choice of key for this query

D.Execute the run_2 index because it has caused a conflict in the choice of key for this query

E.Add a composite index on (run,objective,stage) to allow the query to fully utilize an index


参考答案:E

第2题:

What will be the phase angle relationship of a six-pole, three-phase, rotating field generator?

A.60

B.120

C.180

D.360


正确答案:B

第3题:

● In multi-phase projects, the () Project process closes out the portion of the project scope and associated activities applicable to a given phase.()A.Scope B.Plan C.Close D.Control


正确答案:C
对于多阶段项目,项目收尾过程结束的是同给定阶段对应的部分项目范围和有关活动。

第4题:

Which two service components are in the plan phase?()

  • A、Proof of Concept
  • B、Site Readiness Assessment
  • C、Proposal Development
  • D、Operations Readiness Assessment
  • E、Account planning

正确答案:B,D

第5题:

Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()

  • A、staging and system migration
  • B、post implementation support handoff meeting
  • C、detailed design development
  • D、staff training
  • E、migration plan development

正确答案:A

第6题:

In which phase is a systems acceptance test plan developed and documented? ()

A.Implement

B.Design

C.Prepare

D.Operate


参考答案:B

第7题:

Formulation and exercise of emergency response plan is carried out in( ) phase.


A .planning and design
B. deployment and implementation
C. operation management
D. continuous improvement


答案:B
解析:
应急预案的制定和实施( )阶段。A.计划和设计 B.部署和实施C.运营管理 D.持续改进

第8题:

What should be the objective of a sports team?

A、To make money

B、To develop skills

C、To win

D、To make friends


参考答案:C

第9题:

Which of the following statements that describe Diffie Hellman Key exchange are correct? ()

  • A、 A DH key exchange is an algorithm that utilizes asymmetric cryptographic keys.
  • B、 The DH key exchange is used to establish a shared secret over an insecure medium during an IPSec phase 1 exchange.
  • C、 The DH exchange is susceptible to man-in-the-middle attacks.
  • D、 The DH exchange is used to authenticate the peer device duringan IPSec phase 1 exchange.
  • E、A DH exchange provides Perfect Forward Secrecy (PFS).

正确答案:A,B,C,E

第10题:

Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。

  • A、Detailed Design Development
  • B、Systems Acceptance Test Plan Development
  • C、Staging Plan
  • D、Implementation Plan Development
  • E、Project Kick-off

正确答案:D

更多相关问题