第1题:
Which of the following constitute Juran's "quality trilogy":
A . planning, inspection, control.
B . planning, improvement, control.
C . planning, organization, control.
D . product, price, customer.
E . design, build, deliver.
第2题:
121 Project management/project planning is most closely aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C
第3题:
Project management/project planning is most closely aligned with:
A.Long range/strategic planning ( years or more).
B.Intermediate range planning ( to years)
C.Short range/tactical planning ( year or less).
D.All of the above.
E.B and C.
第4题:
A.material requirement planning。
B.management requirement planning。
C.manufacturing resource planning。
D.material revenue planning。
E.Material risk planning。
第5题:
63 When planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
A. Building multi-disciplinary teams
B. Managing conflict
C. Communicating orally and in writing with all levels of personnel
D. Involving senior management
E. All are important
第6题:
When planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
A . Building multi-disciplinary teams
B . Managing conflict
C . Communicating orally and in writing with all levels of personnel
D . Involving senior management
E . All are important
第7题:
123 Which of the following constitute Juran's "quality trilogy":
A. planning, inspection, control.
B. planning, improvement, control.
C. planning, organization, control.
D. product, price, customer.
E. design, build, deliver.
第8题:
Planning activities such that predetermined resource availability pools are not exceeded is called:
A.Resource leveling.
B.Manpower leveling.
C.Resource limited planning.
D.Manpower planning.
E.Manpower contingency planning.
第9题:
116 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.
B. Manpower leveling.
C. Resource limited planning.
D. Manpower planning.
E. Manpower contingency planning.
第10题:
A.macro planning and micro planning
B.day by day and one week