Refuse to accept the barge until all wing voids are dry
Accept the barge and when weather conditions permit run with the wing voids open to ventilate the spaces
Accept the barge and periodically check the wing voids
Return the barge to the fleet and depart without the barge
第1题:
Hanging a barge off means to ______.
A.moor a damaged barge to the bank and leave
B.remove and deliver a loaded barge from a multiple tow
C.remove a barge while locking through
D.tow an empty barge astern
第2题:
You are making tow.A loaded,open-hopper barge with independent tanks has placards,with alternating red and white quadrants,located at each side and end.You inspect the barge and find slight traces of water in the wing voids due to condensation.What should you do?
A.Refuse to accept the barge until all wing voids are dry
B.Accept the barge and when weather conditions permit run with the wing voids open to ventilate the spaces
C.Accept the barge and periodically check the wing voids
D.Return the barge to the fleet and depart without the barge
第3题:
I don‘t mind _______ the decision as long as it is not too late. A. you to delay making B. your delaying making C. your delaying to make D. you delay to make
第4题:
If you have a liquefied flammable gas barge in tow,which is NOT required of you with respect to the barge and its cargo ________.
A.Make periodic inspections of bilges
B.Keep the barge under constant surveillance
C.Have a properly certificated tankerman or at least one licensed officer on board the towing vessel
D.Verify ullage readings
第5题:
You are berthed at a cargo facility where you have just completed discharging a dangerous cargo from your barge.You must complete topside repairs on the barge involving hot work before sailing.Which statement is TRUE ________.
A.You can make repairs with permission of the facility owner since you are empty and the cargo is on the facility
B.The repair area must be inspected by a marine surveyor to ensure that it can be done safely
C.Hot work repairs at such a facility are prohibited
D.The Captain of the Port may give specific approval to make hot work repairs
第6题:
While underway and towing an unmanned tank barge you are required to ______.
A.maintain a strict watch on the barge from the towing vessel
B.fly a red flag from the towing vessel
C.open the tops of all empty tanks on the barge
D.take hourly soundings of any loaded tanks on the barge
第7题:
You are in the process of adding a barge to your tow.A line run from your power capstan and around timber heads on your tow is made fast on the new barge so that it can be pulled into position.This line is called a ______.
A.Scissors wire
B.Capstan line
C.Spring line
D.Fore and aft line
第8题:
What is NOT accepted as the required shipping papers on a manned and loaded tank barge? ______.
A.Bill of Lading
B.Manifest
C.Shipping document
D.Logbook entry
第9题:
Your tow includes a loaded chlorine barge.After inspecting the tow,the mate reports that he hears a hissing sound coming from the safety valves.Where will you find information on emergency procedures concerning the uncontrolled release of cargo ________.
A.Barge's Certificate of Inspection
B.Cargo Information Card on your towboat
C.Cargo Manifest or loading paper
D.Dangerous Cargo Regulations
第10题:
You are operating a lift boat.When jacking down and a leg becomes stuck on the bottom,you should ______.
A.raise the free legs all the way
B.use the engines to rotate about the leg that is stuck
C.jack the barge down part way to pull the leg free
D.submerge the barge completely to give added pull