No claim for constructive total loss based upon the cost of

题目
单选题
No claim for constructive total loss based upon the cost of recovery and/or repair of the Vessel shall be recoverable hereunder unless such cost would exceed().
A

the stated value

B

the sound valve of the vessel at the time of occurrence

C

the lost value

D

the insured value

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.

A . Definitive, bottom up.

B . Analogy, top down.

C . Parametric, bottom up.

D . Parametric, top down.

E . Analogy, bottom up.


正确答案:D

第2题:

50 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.

A. Definitive, bottom up.

B. Analogy, top down.

C. Parametric, bottom up.

D. Parametric, top down.

E. Analogy, bottom up.


正确答案:D

第3题:

The scope of a project can be expected to change if:

A.The project manager must provide cost estimates without having a design concept

B.Oversimplification (underestimating) of the nature of the work occurs

C.The project manager is assigned after the project is defined, and the cost and schedule are approved

D.A clear objective is not provided

E.All of the above are possible based upon the situation


正确答案:E

第4题:

总固定成本〔Total cost)


参考答案:

总固定成本是指每个时期厂商在不变投入品上的总支出。


第5题:

123 The scope of a project can be expected to change if:

A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

C. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not provided

E. All of the above are possible based upon the situation


正确答案:E

第6题:

104 A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:

A. A shortening of the critical path.

B. A shortening of the noncritical path.

C. A decrease in the total cost of the project.

D. An increase in the cost of the project.

E. A through D are possible based upon where the resources are deployed


正确答案:E
i

第7题:

41 The scope of a project can be expected to change if:

A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

C. The project manager is assigned after the project is defined, and the cost and schedule are approved

D. A clear objective is not provided

E. All of the above are possible based upon the situation


正确答案:E

第8题:

A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from to . This will result in:

A.A shortening of the critical path.

B.A shortening of the noncritical path.

C.A decrease in the total cost of the project.

D.An increase in the cost of the project.

E.A through D are possible based upon where the resources are deployed.


正确答案:E
E

第9题:

● The scope of a project can be expected to change if:

A The project manager must provide cost estimates without having a design concept

B Oversimplification (underestimating) of the nature of the work occurs

C The project manager is assigned after the project is defined, and the cost and schedule are approved

D A clear objective is not provided

E All of the above are possible based upon the situation


正确答案:E

第10题:

By default, which of the following factors determines the spanning-tree path cost?

A.It is the individual link cost based on latency

B.It is the sum of the costs based on bandwidth

C.It is the total hop count

D.It is dynamically determined based on load

E.None of the above


正确答案:B
解析:Explanation:"TheSTPcostisanaccumulatedtotalpathcostbasedontheavailablebandwidthofeachofthelinks."Note:Apathcostvalueisgiventoeachport.Thecostistypicallybasedonaguidelineestablishedaspartof802.1d.Accordingtotheoriginalspecification,costis1,000Mbps(1gigabitpersecond)dividedbythebandwidthofthesegmentconnectedtotheport.Therefore,a10Mbpsconnectionwouldhaveacostof(1,000/10)100.Tocompensateforthespeedofnetworksincreasingbeyondthegigabitrange,thestandardcosthasbeenslightlymodified.Thenewcostvaluesare:Youshouldalsonotethatthepathcostcanbeanarbitraryvalueassignedbythenetworkadministrator,insteadofoneofthestandardcostvalues.IncorrectAnswers:A,D:TheSTPprocessdoesnottakeintoaccountthelatencyorloadofalink.STPdoesnotrecalculatethelinkcostsdynamically.C.HopcountsareusedbyRIProuterstocalculatethecostofaroutetoadestination.TheSTPprocessresidesatlayer2oftheOSImodel,wherehopcountsarenotconsidered.

更多相关问题