You are discharging cargo and the inert gas system is in ope

题目
单选题
You are discharging cargo and the inert gas system is in operation to inert the tanks. The pressure in a tank being discharged starts to drop below the allowable limit. What action should you take? ()
A

Cut in another IG fan to increase gas flow

B

Open the pressure control valve until the pressure increases

C

Open the tank isolation valve to the fully open position

D

Reduce the pumping rate

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

You are discharging cargo and the inert gas system is in operation to inert the tanks. The pressure in a tank being discharged starts to drop below the allowable limit. What action should you take?

A.Cut in another IG fan to increase gas flow

B.Open the pressure control valve until the pressure increases

C.Open the tank isolation valve to the fully open position

D.Reduce the pumping rate


正确答案:D

第2题:

Inerting means ______.

A.The introduction of inert gas into a tank with the object of reducing the oxygen content to below 8% by volume

B.The introduction of inert gas into a gas free tank for the purpose of reducing the oxygen content to below 8% by volume

C.The introduction of inert gas into a cargo tank during cargo discharge to replace the volume of discharged cargo

D.All of the above


正确答案:D

第3题:

How does an inert gas system on a tanker function to prevent explosions in cargo tanks?

A.De-energizes the "charged mist" effect

B.Maintains a positive pressure on the vent header to cool the flammable vapors

C.Inert gas filters out the flammable vapors from the cargo tank spaces

D.Inert gas dilutes the flammable vapor and air concentrations to keep them below the lower explosive limit


正确答案:D

第4题:

Which statement about inert gas pressures in a cargo tank is TRUE ________.

A.The pressures of the inert gas in the tank may create excessive pressure at the pump while discharging

B.Gas pressures should be maintained at the highest permissible level throughout the discharging process

C.High gas pressures may cause pyrophoric oxidation in the tank

D.High gas pressures may cause loss of suction when stripping


正确答案:B

第5题:

The deck water seal of the inert gas system ______.

A.Cools the inert gas and prevents soot from entering the cargo tanks

B.Acts as an emergency shutdown when inlet pressures exceed the safe working pressure

C.Prevents the backflow of hydrocarbon gasses into nonhazardous areas

D.Relieves sudden large overpressures in the system


正确答案:C

第6题:

______ shall be provided in every cargo tank and slop tank in accordance with the appropriate Resolutions.

A.A load on top system

B.Direct line system

C.Circle line system

D.An inert gas system


正确答案:D

第7题:

The blowers of an inert gas generation system aboard a tanker,will be automatically secured if ______.

A.Normal water supply at the water seal is lost

B.The temperature of the inert gas being delivered to the cargo tanks is more than 150℉

C.The cooling water supply to the scrubbers is lost

D.All of the above


正确答案:D

第8题:

Which method is used to supply inert gas from a flue gas system to the cargo tanks?

A.Exhaust gas pressure from the stack

B.High capacity fan

C.Inert gas compressor

D.Natural aspiration


正确答案:B

第9题:

Upon arrival at the discharging port,the inert gas system is ______.

A.Turned on

B.Turning on

C.Turn on

D.To turn on


正确答案:A

第10题:

The venting system shall be provided with devices to prevent the passage of ______ into the cargo tanks.

A.flame

B.inert gas

C.air

D.oil gas


正确答案:A