A co-worker is developing an implementation plan for a desig

题目
单选题
A co-worker is developing an implementation plan for a design that uses OSPF 2 and RIPv2 routing domains, with two routers redistributing between the two domains.The co- worker asks your help in choosing how to prevent domain loops by setting administrative distance. Assuming all other related settings use defaults, which of the following would solve the domain loop problem?()
A

The distance ospf intra - area 80 inter - area 80 OSPF subcommand

B

T he distance ospf external 80 OSPF subcommand

C

The distance ospf intra - area 180 inter - area 180 OSPF subcommand

D

The distance ospf external 180 OSPF subcommand

参考答案和解析
正确答案: B
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● The sequential steps that define the process for successfully completing a project is:

A Implementation Plan

B a life cycle

C Development Plan

D a critical path

E Management Plan


正确答案:B

第2题:

You are developing a verification plan for an upcoming OSPF implementation. Part of this plan is to verify the status of type 3 LSAs within the network. Which routers should you verify first to ensure that the configuration s are correct for generating type 3 LSAs?()

A. Internal routers within the backbone area (area 0)

B. Internal routers within the NSSAs

C. Internal routers within the stubby areas

D. ASBRs

E. ABRs

F. DRs and BDRs


参考答案:E

第3题:

The sequential steps that define the process for successfully completing a project is:

A.Implementation Plan

B.a life cycle

C.Development Plan

D.a critical path

E.Management Plan


正确答案:B
B

第4题:

What is a critical piece of information that you should have when creating a VLAN-based implementation plan?()

  • A、approval from senior management
  • B、end-user requirements
  • C、IEEE 802.1X authentication parameters
  • D、a summary implementation plan

正确答案:D

第5题:

Which definition best describes the implementation service component within the implement phase? Select exactly 1 answer(s) from the following:()。

  • A、providing a step-by-step plan that details the installation and service-commission tasks required in order to create a controlled-implementation environment that emulates a customer network
  • B、assessing the ability of site facilities to accommodate proposed infrastructure changes
  • C、developing and executing proof-of-concept tests, validating high-level infrastructure design, and identifying any design enhancements
  • D、installing, configuring, and integrating systems components based on an implementation plan developed in earlier phases
  • E、improving a customer’s infrastructure security system

正确答案:D

第6题:

An engineer is preparing an implementation plan in which the configuration needs to influence BGP‘s choice of best path.Which of the following is least likely to be used by the configuration in this imple mentation plan?()

A. Weight

B. Origin code

C. AS_Path

D. Local_Pref


参考答案:B

第7题:

Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coordinating change implementation, monitoring and reporting on implementation, reviewing and closing ().


A. change reason
B. change model
C. remediation plan
D. change requests


答案:D
解析:

第8题:

115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan

B. a life cycle

C. Development Plan

D. a critical path

E. Management Plan


正确答案:B

第9题:

Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()

  • A、staging and system migration
  • B、post implementation support handoff meeting
  • C、detailed design development
  • D、staff training
  • E、migration plan development

正确答案:A

第10题:

Which definition best describes the staging plan development service component within the design phase? Select exactly 1 answer(s) from the following:()。

  • A、providing a step-by-step plan that details the installation and service-commission tasks required in order to create a controlled-implementation environment that emulates a customer network
  • B、assessing the ability of site facilities to accommodate proposed infrastructure changes
  • C、developing and executing proof-of-concept tests, validating high-level infrastructure design, and identifying any design enhancements
  • D、improving the network management system and the performance and functionality of infrastructure operations

正确答案:A

更多相关问题