单选题In the video form. the OrderDate field (Which shows When the video may be ordered)is calculated based on the Date field (Which displays the release date ). The order date is 30 days prior to  the release date. Which one the following formulas will calc

题目
单选题
In the video form. the OrderDate field (Which shows When the video may be ordered)is calculated based on the Date field (Which displays the release date ). The order date is 30 days prior to  the release date. Which one the following formulas will calculate the OrderDate value?()
A

@Number(Date)-30       

B

@Adjust(Date;0;0;30;0;0;0) 

C

@Adjust(Date;0;0;-30;0;0;0) 

D

@If(Date!=;Date-30;@Failure(There is no current release date)) 

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Which of the following is indicative of negative float?

A The late start date is earlier than the early start date.

B The critical path supports the imposed end date.

C The early finish date is equal to the late finish date.

D When leads are employed in the schedule.

E The project is sinking.


正确答案:A

第2题:

The day on which the board of directors of the corporation distributes a dividend is called the declaration date.()

此题为判断题(对,错)。


正确答案:错误

第3题:

Which of the following is indicative of negative float?

A.The late start date is earlier than the early start date.

B.The critical path supports the imposed end date.

C.The early finish date is equal to the late finish date.

D.When leads are employed in the schedule.

E.The project is sinking.


正确答案:A
A

第4题:

Which of the following require physical CD/DVD media to be ordered and received prior to patching and/or upgrading IPCC Express 4.0?()

  • A、Major Release  
  • B、Minor Release  
  • C、Maintenance Release  
  • D、Service Release  
  • E、Engineering Special

正确答案:A,B

第5题:

We have accepted your Order No.TR22.Please open the relative L/C,()here four weeks before the date of shipment.

A、that should reach

B、which should reach

C、when it reaches

D、which should arrive at


参考答案:B

第6题:

● The critical path is calculated by

A subtracting the end date of task one from the start date of task two.

B determining which tasks have the least amount of total slack.

C totaling the time for all activities.

D determining the shortest path through the network.

E Determining which tasks have the most slack


正确答案:B

第7题:

The liability for a dividend is recorded on which of the following dates?()

A、the date of record

B、the date of payment

C、the date of announcement

D、the date of declaration


正确答案:D

第8题:

The critical path is calculated by

A.subtracting the end date of task one from the start date of task two.

B.determining which tasks have the least amount of total slack.

C.totaling the time for all activities.

D.determining the shortest path through the network.

E.Determining which tasks have the most slack


正确答案:B
B

第9题:

In the video form. the OrderDate field (Which shows When the video may be ordered)is calculated based on the Date field (Which displays the release date ). The order date is 30 days prior to  the release date. Which one the following formulas will calculate the OrderDate value?()

  • A、@Number(Date)-30       
  • B、@Adjust(Date;0;0;30;0;0;0) 
  • C、@Adjust(Date;0;0;-30;0;0;0) 
  • D、@If(Date!="";Date-30;@Failure(There is no current release date")) 

正确答案:C

第10题:

Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()

  • A、 elapsed time since the target start date or completion date of previous work generated by PM  
  • B、 difference between completion date of previous work and system date is equal to Lead Time  
  • C、 elapsed time since the target start date or completion date of the latest work orders for the asset
  • D、 metered equipment usage since the target start date or completion date of previous work generated by PM
  • E、 metered equipment usage since the target start date or completion date of the latest work order for the asset

正确答案:A,D