单选题Which of the following interfaces is required to implement Workload Partition Mobility? ()A  Workload Partitions Manager for AIXB  Hardware Management Console (HMC) GUIC  Integrated Virtualization Manager (IVM)D  Advanced System Management Interface (A

题目
单选题
Which of the following interfaces is required to implement Workload Partition Mobility? ()
A

 Workload Partitions Manager for AIX

B

 Hardware Management Console (HMC) GUI

C

 Integrated Virtualization Manager (IVM)

D

 Advanced System Management Interface (ASMI)

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()

  • A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).
  • B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).
  • C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).
  • D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

正确答案:A

第2题:

Which of the following functions can be performed using the Integrated Virtualization Manager?()

  • A、Concurrent firmware updates
  • B、Management of virtual storage
  • C、Hot add/remove of I/O drawers
  • D、Management of Capacity on Demand

正确答案:B

第3题:

A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

  • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
  • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
  • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
  • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

正确答案:D

第4题:

Company.com has a single pSeries server with two shared processor logical partitions. The first partition has peak resource requirements during weekdays. The second partition has peak resource requirements during weekends. During the peak times, the total workload between the partitions does NOT exceed the capacity of the server. However, the partitions are not able to utilize the full capacity of the system during peak times, because the necessary CPU and memory resources are not always allocated to the busiest partition. Which of the following options would best balance these resources?()

  • A、Configure AIX Workload Manager
  • B、Configure Partition Load Manager
  • C、Configure eServer Workload Manager
  • D、Use DLPAR from the HMC

正确答案:B

第5题:

A customer recently acquired two Power servers and plans to implement AIX 6.1 and Live Application Mobility.  What other product is required to accomplish this objective? ()

  • A、 HACMP for AIX
  • B、 PowerVM Enterprise Edition
  • C、 IBM Management Edition for AIX
  • D、 Workload Partition Manager for AIX

正确答案:D

第6题:

Prior to implementing an LPAR system, which of the following needs to be done?()

  • A、A graphics monitor must be attached to the server
  • B、Cluster System Management (CSM) software must be installed
  • C、The LPAR system must have an Hardware Management Console (HMC) connected
  • D、Each LPAR must be configured with a CDROM for operating system installation

正确答案:C

第7题:

Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems?()

  • A、The systems must use internal storage for boot purposes. 
  • B、All virtualized ethernet adapters must be numbered below 10. 
  • C、The mobile partition's network and disk access must be virtualized. 
  • D、Each system must be controlled by a different Hardware Management Console (HMC). 

正确答案:C

第8题:

An IT manager needs to deploy multiple applications simultaneously. Which virtualization technology will reduce the number of operating system maintenance tasks?()

  • A、Workload partitions
  • B、Dynamic logical partitions
  • C、Dedicated logical partitions
  • D、Virtualized logical partitions

正确答案:A

第9题:

Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()

  • A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 
  • B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 
  • C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 
  • D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

正确答案:B

第10题:

Which of the following virtualization options are unique to AIX and PowerVM compared to other UNIX based offerings?()

  • A、Software virtualization through PowerVM and hardware virtualization through IBM Systems Director.
  • B、Hardware virtualization through Workload Partitions (WPARS) and software virtualization through PowerVM.
  • C、Software virtualization through Workload Partitions (WPARS) and hardware virtualization through PowerVM.
  • D、Hardware virtualization through Workload Partitions (WPARS) and software virtualization through IBM Systems Director.

正确答案:C