单选题Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()A  It has a GUI interface for upgrading system firmware. B  It creates and manages AIX/Linux and VIOS type LPARs. C  It can be managed by the Hardware Management Console 

题目
单选题
Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()
A

 It has a GUI interface for upgrading system firmware. 

B

 It creates and manages AIX/Linux and VIOS type LPARs. 

C

 It can be managed by the Hardware Management Console (HMC). 

D

 It supports Live Partition Mobility on POWER6 systems and above.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

  • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
  • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
  • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
  • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

正确答案:D

第2题:

Which operating system can directly host managed storage for IBM i, AIX, Linux, VMware and Windows on a Power Systems server?()

  • A、AIX
  • B、IBM i
  • C、Linux
  • D、VIO Server

正确答案:B

第3题:

On which product media can the IVM install code be located?()

A.Base AIX Install media.

B.Base VIOS Install media.

C.AIX Expansion Pack media.

D.VIOS Expansion Pack media.


参考答案:B

第4题:

A system administrator has just finished upgrading a system to AIX 5.2. If there are future problems, the system administrator would like to add an entry to the AIX errorlog to record this event. Which of the following commands can be issued for this purpose?()

  • A、/usr/bin/errmsg "System upgraded to AIX 5.2"
  • B、/usr/bin/errlog "System upgraded to AIX 5.2"
  • C、/usr/bin/errupdate "System upgraded to AIX 5.2"
  • D、/usr/bin/errlogger "System upgraded to AIX 5.2"

正确答案:D

第5题:

Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()

  • A、Use the Advanced Systems Management Interface to enter the Capacity on Demand Enablement code.
  • B、Use the Web-based System Manager Interface to enter the Capacity on Demand enablement code.
  • C、Use smitty or smit interface to enter the Capacity on Demand enablement code.
  • D、Use oem_setup_env on the Virtual I/O Server to enter the Capacity on Demand enablement code.

正确答案:A

第6题:

Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()

  • A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).
  • B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).
  • C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).
  • D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

正确答案:A

第7题:

Which of the following functions can be performed using the Integrated Virtualization Manager?()

  • A、Concurrent firmware updates
  • B、Management of virtual storage
  • C、Hot add/remove of I/O drawers
  • D、Management of Capacity on Demand

正确答案:B

第8题:

On which product media can the IVM install code be located?()

  • A、Base AIX Install media.
  • B、Base VIOS Install media.
  • C、AIX Expansion Pack media.
  • D、VIOS Expansion Pack media.

正确答案:B

第9题:

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

  • A、p5 hardware, AIX 5.2, Virtual I/O Server
  • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
  • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
  • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

正确答案:C

第10题:

Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()

  • A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 
  • B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 
  • C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 
  • D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

正确答案:B