Software configuration management(SCM),is the task of tracking and controiling changes in the software,configuration management practicesconfiguration identirication change control ()and configuration audit
A.ailestones marking
B.status reporting
C.stakeholder management
D.quality audit
第1题:
● The purpose of configuration management is to:
A insure drawings are updated
B control change throughout the project
C control change during the production only
D generate engineering change proposals
E inform. the project manager of changes
第2题:
● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.
(74)
A.Rational Clearcase
B.Quality Function Deployment
C.Visual SourceSafe
D.Concurrent Versions System
第3题:
The purpose of configuration management is to:
A.insure drawings are updated
B.control change throughout the project
C.control change during the production only
D.generate engineering change proposals
E.inform. the project manager of changes
第4题:
Configuration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of(75) identification.
A.baseline
B.value
C.cost
D.control
第5题:
● __(73)__ are the four major activities of software configuration management.
①configuration identification ②statement report ③change control
④preparation of requirement document ⑤configuration auditing
(73)A.①②③④ B.①②④⑤ C.①②③⑤ D.②③④⑤
第6题:
● Configuration management is the process of managing change in hardware, software, firmware, documentation, measurements, etc. As change requires an initial state and next state, the marking of significant states within a series of several changes becomes important. The identification of significant states within the revision history of a configuration item is the central purpose of (75) identification.
(75)
A. baseline
B. value
C.cost
D. control
第7题:
After making some network changes you power off and then power on your Cisco router named VE1. What sequence of events occurs when VE1 is powered up?
A. Perform. POST, locate configuration statements, apply configuration statements, locate Cisco IOS software, and load Cisco IOS software.
B. Locate Cisco IOS software, load Cisco IOS software, locate configuration statements, apply configuration statements, and perform. POST.
C. Test software routines, POST, load configuration files, load Cisco IOS software, test Cisco IOS software.
D. Perrform. POST, locate Cisco IOS software, load the Cisco IOS software, locate configuration statements, and apply configuration statements.
E. Load and test IOS, load configuration files, test software routines, POST.
F. None of the above
第8题:
A.RationalClearcase
B.QualityFunctionDeployment
C.VisualSourceSafe
D.ConcurrentVersions System
第9题:
Software configuration management(SCM) is the task oftracking and controlling changes in the software. Configuration managementpractices include configuration identification,change control ,(74)and configuration audit.
A.milstones marking
B.status reporting
C.stakeholder management
D.quality audit
第10题:
Network management helps you to(66)the strengths and weaknesses of your network, as well as determine any configuration changes that may be necessary. Any controlled changes to your network and its components-especially configurations, software and(67), can have an effect on its overall efficiency. To maintain control, you need the tools and knowledge to manage all activity that has the potential to affect your(68).
A.see
B.know
C.monitor
D.control