Project Quality Management must address the management of the project and the(72)of the pr

题目

Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

A.performance

B.process

C.product

D.object

参考答案和解析
正确答案:C
解析:项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not (72 ).

(72)

A. executed in

B. inspected in

C. check-in

D. look-in


正确答案:B

第2题:

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A.Project

B.project management team

C.performingorganization

D.customer


参考答案:C

该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

第3题:

The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A . budget, schedule

B . quality requirements, schedule

C . size, type of industry

D . nature, size

E . project manager, sponsor


正确答案:D

 

第4题:

The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


正确答案:B
制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

第5题:

● The inputs of developing project management plan do not include (72).

(72)

A. project charter

B. stakeholder management strategy

C. project scope statement

D. outputs from planning processes


正确答案:B

第6题:

69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A. budget, schedule

B. quality requirements, schedule

C. size, type of industry

D. nature, size

E. project manager, sponsor


正确答案:D

第7题:

● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

A.performance

B.process

C.product

D.object


正确答案:C

第8题:

● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

(71)

A. project

B. project management team

C. performing organization

D. customer


正确答案:C

第9题:

The inputs of developing project management plan do not include (72) .

A.project charter

B.stakeholder management strategy

C.project scope statement

D.outputs from planning processes


正确答案:B

第10题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。