If a vessel takes a sudden severe list or trim from an unknown cause, you should FIRST____.
A.determine the cause before taking countermeasures
B.assume the shift is due to off-center loading
C.counterflood on the side opposite the list or trim
D.assume the cause is environmental forces
第1题:
During cargo operations,your vessel develops a list due to the center of gravity rising above the transverse metacenter.To correct the list,you should ______.
A.Shift weight to the high side
B.Shift weight to the centerline
C.Add weight in the lower holds or double bottoms
D.Remove weight from the lower holds or double bottoms
第2题:
For a vessel with transverse inclination, an increase in GMT causes ______.
A.list to stabilize at an angle of loll
B.trim to decrease
C.list to increase
D.list to decrease
第3题:
A negative metacentric height ______.
A.should always be immediately corrected
B.will always cause a vessel to capsize
C.always results from off-center weights
D.All of the above are correct
第4题:
press up a slack double bottom tank on the port side
fill an empty centerline double bottom tank
pump out a slack marine portable tank located on the portside amidships
jettison the anchors and anchor cables
第5题:
Call the Master and the deck gang
Slip the stern lines,let the vessel drift into the river,and then anchor
Let go the starboard anchor
Obtain assistance and attempt to put some new bow lines out
第6题:
For a vessel with longitudinal inclination, an increase in GML causes ______.
A.list to stabilize at an angle of loll
B.trim to stabilize at an angle of loll
C.trim to increase
D.trim to decrease
第7题:
You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.Company.com has recently attempted the creation of a new address list based on the network user’s country attribute but discovered that the attribute is not available in the New Address List Wizard.During the course of the business week you receive instruction from Company.com to create a new address list based on the network user’s country. What should you do?()
第8题:
While your vessel is docked port side to a wharf,a sudden gale force wind causes the vessel's stern lines to part. The stern begins to fall away from the dock,and no tugs are immediately available. Which measure(s) should you take FIRST?
A.Notify the engineroom of the need for propulsion
B.Shut down any cargo transfer that's in progress
C.Let go the port anchor and veer to a short scope of chain
D.Obtain assistance from the terminal to put new stern lines out
第9题:
The slowing is only temporary and the vessel will probably suddenly capsize or plunge from loss of stability due to change in the waterplane area
The vessel can probably be saved if further flooding can be stopped
The vessel will continue to slowly list and/or trim due to the free surface effect and free communication effect
The vessel will suddenly flop to the same or greater angle of list on the other side and may capsize
第10题:
Two to four feet by the bow
Slightly by the bow
No trim should be permitted
Slightly by the stern