( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

题目
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of the following would most likely increase the accuracy of estimating the project cost?

A . Pricing out the work at lower levels in the work breakdown structure.

B . Using historical data.

C . Talking to people who have worked on similar projects.

D . All of the above.

E . A and C only.


正确答案:D

第2题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


参考答案:B

第3题:

Sources for data on activity durations and resource requirements can be gathered from which of the following:

A.Past project records (historical data)

B.Commercial techniques (standard practices, rules of thumb)

C.Past project team members knowledge (experience, oldtimers)

D.All of the above

E.A and C only


正确答案:D
D

第4题:

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work


正确答案:D
解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

第5题:

● Sources for data on activity durations and resource requirements can be gathered from which of the following:

A Past project records (historical data)

B Commercial techniques (standard practices, rules of thumb)

C Past project team members knowledge (experience, oldtimers)

D All of the above

E A and C only


正确答案:D

第6题:

87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.

B. Using historical data.

C. Talking to people who have worked on similar projects.

D. All of the above.

E. A and C only.


正确答案:D

第7题:

151 Sources for data on activity durations and resource requirements can be gathered from which of the following:

A. Past project records (historical data)

B. Commercial techniques (standard practices, rules of thumb)

C. Past project team members knowledge (experience, oldtimers)

D. All of the above

E. A and C only


正确答案:D

第8题:

Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

A . P

B . Q

C . R

D . S

E . T


正确答案:A

第9题:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development


正确答案:D

第10题:

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


正确答案:B
试题(71)分析
 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
 项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
 以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
参考答案
(71)B

更多相关问题