第1题:
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第2题:
● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work
第3题:
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第4题:
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
A.accuracy
B.approximation
C.specification
D.summary
第5题:
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)
A.activity duration estimating, schedule developing, activity resource estimating
B . activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第6题:
Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
第7题:
Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().
A.expert judgment
B.analogous estimating
C.requiremen tstraceability matrix
D.three-point estimating
第8题:
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
第9题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第10题:
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
A.accuracy
B.approximation
C.specification
D.summary