Estimating activity

题目
Estimating activity
durations uses information on activity scope of ( ) , required resource types, estimated
resource quantities, and resource calendars.

A.milestone
B. baseline
C.quality
D. work
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development


正确答案:D

第2题:

● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.

(74)

A. milestone

B. baseline

C. quality

D. work


正确答案:D


 

 

第3题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


参考答案:B

第4题:

Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.

A.accuracy

B.approximation

C.specification

D.summary


正确答案:B
解析:估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本。成本估算包括识别和考虑各种成本计算方案。例如,在大多数的应用领域,普遍在设计阶段多做些额外工作以降低执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般以货币单位表示,以利于在项目内和项目间进行比较。项目范围说明书描述了项目的商业要求、理由、需求和当前边界。它提供了关于在成本估算时必须考虑的项目需求的重要信息。

第5题:

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


正确答案:B
试题(71)分析
 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
 项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
 以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
参考答案
(71)B

第6题:

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work


正确答案:D
解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

第7题:

Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A.expert judgment

B.analogous estimating

C.requiremen tstraceability matrix

D.three-point estimating


正确答案:C

第8题:

● (73) is one of the techniques used for estimating activity durations.

(73)

A.Analogous Estimating

B.Precedence Diagramming Method (PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
试题(73)分析
    下列用于活动历时估算的技术是答案A类比估算法。
参考答案
    (73)A

第9题:

______is one of the techniques used for estimating activity durations.

A.Analogous Estimating

B.Precedence Diagramming Method(PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
解析:下列用于活动历时估算的技术是答案A类比估算法。

第10题:

Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.

A.accuracy

B.approximation

C.specification

D.summary


正确答案:B

更多相关问题