The()process differs from the()process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with acceptance of the deliverables,while

题目
The()process differs from the()process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.

A.perform Quality Assurance
B.Validate Scope
C.Control Quality
D.Define Scope
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

(71)

A. project elements

B. work drafts

C. work package

D. project deliverables


正确答案:D

第2题:

______is primarily concerned with defining and controlling what is and is not included in the project.

A.Project Time Management

B.Project Cost Management

C.Project Scope management

D.Project Communications Management


正确答案:C
解析:项目范围管理是项目管理(包括时间、成本、沟通)的基础。
  项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
  选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理,因此应选择C。

第3题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


正确答案:B

第4题:

Managerial accounting is primarily concerned with the recording and reporting of economic data and activities of an entity for use by owners, creditors, governmental agencies, and the public.()


正确答案:错

第5题:

The superordinate differs from the subordinate in that the former covers theconcept of the latter.( )

此题为判断题(对,错)。


正确答案:正确

第6题:

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

A.WBS Creation

B.Scope definition

C.Project acceptance

D.Scope verification


正确答案:D

第7题:

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

A.work performance information

B.scope statement

C.change requests

D.process analysis


正确答案:B
解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

第8题:

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

A.project elements

B.work drafts

C.work package

D.project deliverables


正确答案:D
解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

第9题:

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。

A、Validate scope

B、Define scope

C、Control scope

D、Collect requirement


正确答案:C

第10题:

the () is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables

A.verify scope

B.define scope

C.quality assurance

D.validate scope


正确答案:A
解析:()是接受可交付成果主要考虑的因素。质量控制主要考虑可交付成果的正确性,并关注可交付物符合质量需求的程度A、确认范围B、定义范围C、质量保证D、验证范围

更多相关问题