第1题:
Cost and schedule data are usually integrated because:
A.optimized project cash flow can affect financial requirements
B.they provide MIS with an integrated system to produce reports
C.they control escalation allowances
D.they account for omissions in the definitive estimate
E.they predict future performance
第2题:
61 Cost and schedule data are usually integrated because:
A. optimized project cash flow can affect financial requirements
B. they provide MIS with an integrated system to produce reports
C. they control escalation allowances
D. they account for omissions in the definitive estimate
E. they predict future performance
第3题:
Including the customer in the process of project planning is:
A.Slow and counterproductive.
B.Essential in the definition and documentation of project goals.
C.Necessary, but of limited value.
D.Unnecessary because project goals are defined in the proposal stage.
E.None of the above.
第4题:
● Including the customer in the process of project planning is:
A Slow and counterproductive.
B Essential in the definition and documentation of project goals.
C Necessary, but of limited value.
D Unnecessary because project goals are defined in the proposal stage.
E None of the above.
第5题:
(A) finance
(B) financial
(C) money
(D) economical
正确答案:B
解答参考:finance n.“金融,财政”,financial adj.“金融的,财政的”,economical adj.“节约的”。【译文】公司处于财政困难中。
第6题:
109 Problems can occur in properly defining a project because:
A. Project goals may not be agreeable to all parties
B. The plan was "too loose," thus allowing priorities to change
C. Low turnover of project personnel
D. Too much communication between the client and project personnel
E. The project objectives were quantified
第7题:
A.Because of
B.In proportion with
C.As a result of
D.In spite of
第8题:
The financial closeout of a project dictates that:
A.All project funds have been spent.
B.No charge numbers have been overrun.
C.No follow-on work from this client is possible.
D.No further charges can be made against the project.
E.All of the above.
第9题:
● Problems can occur in properly defining a project because:
A Project goals may not be agreeable to all parties
B The plan was "too loose," thus allowing priorities to change
C Low turnover of project personnel
D Too much communication between the client and project personnel
E The project objectives were quantified
第10题:
● The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.