Team selection is not just a function of finding someone whos a technical or administrative expert. What will a project sponsor leading a high visibility project look for in a project manager?()A、Developing key personnelB、Leading technical specialistsC、In

题目

Team selection is not just a function of finding someone whos a technical or administrative expert. What will a project sponsor leading a high visibility project look for in a project manager?()

  • A、Developing key personnel
  • B、Leading technical specialists
  • C、Interfacing with customers / sponsors
  • D、Analyzing skills
参考答案和解析
正确答案:C
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user


正确答案:E
E

第2题:

Which of the following can the project manager use as a means of measuring project team effectiveness?

A . Absenteeism

B . Sponsor-approved salary increases

C . Efficiency of the team

D . Turnover of personnel

E . Grievances


正确答案:C

第3题:

The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A . budget, schedule

B . quality requirements, schedule

C . size, type of industry

D . nature, size

E . project manager, sponsor


正确答案:D

 

第4题:

Expectancy theory as applied to project management implies that:

A The team will work the hardest on those goals that are clearly explained by the project manager

B The more rewards that the project manager provides, the better the performance of the team

C Team members will work hardest for those project goals that also bring satisfaction to personal goals

D Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members

E None of the above


正确答案:C

第5题:

The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

A . Proposed salary increases if the project is successful

B . Bonuses for early completion date

C . A promise of future assignments

D . Well-defined project objectives

E . Linear responsibility charts


正确答案:D

第6题:

Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

A.The project manager and project office personnel.

B.The project team and functional managers.

C.The project sponsor.

D.All of the above.

E.A and B only.


正确答案:E
E

第7题:

A life cycle project manager tends to have the following characteristics:

A . balanced training

B . stronger administrative skills than technical skills

C . stronger technical skills than administrative skills

D . stronger human resource skills

E . None of the above.


正确答案:B

第8题:

The appointment or selection of a project sponsor is often based upon:

AThe strategic importance of the project

BWho the customer is

CWhether the organization is project or non-project-driven

DThe profitability of the project

EAll of the above


正确答案:E

 

第9题:

Project managers need exceptionally good communication and negotiation skills primarily because:

A . They may be leading a team over which they have no direct control

B . Procurement activities mandate this

C . They are expected to be technical experts

D . They must provide executive/customer/sponsor briefings

E . All of the above


正确答案:A

第10题:

The Project Manager has the responsibility of knowing what kind of message to send because his _____ may avoid communications barriers.

A business interfaces

B output

C technical experience

D priorities

E training methods


正确答案:B