第1题:
A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()
第2题:
A customer is interested in obtaining an AIX solution from IBM. They have two primary global requirements: ? Availability (although HACMP is not required) ? Low cost Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()
第3题:
A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment.What IBM solution should be recommended to this customer?()
A. Metro Mirror
B. Metro/Global Mirror
C. Geographically Dispersed Open Servers (GDOS)
D. Geographically Dispersed ParallelSysplex (GDPS)
第4题:
A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()
第5题:
The customer is planning a new IBM System Storage DS5020 using iSCSI and direct attachedfibre channel connectivity in a redundant configuration. The customer is planning to set up adisaster recovery solution in the near future by using Enhanced Remote Mirroring. Which of thefollowing considerations are critical for this customer?()
第6题:
The pSeries technical specialist just finished reviewing the system configurations with the customer. The customer requested that many of the availability options,initially configured,be removed due to budgetary constraints. What should be done next?()
第7题:
A customer has a requirement for Disaster Recovery for compliance within their industry. Theyhave an RPO of 4 hours and an RTO of 24 hours. Cost is a consideration. What is the most costeffective DR implementation?()
第8题:
The pSeries sales representative has done an excellent job in educating the customer on the benefits of working with IBM. The customer is planning to implement their first ERP application. This new application will be critical to running their business. The customer has only a competitor’s UNIX systemcurrently installed. They are interested in obtaining a proposal from IBM. In addition to the AIX hardware and HACMP software, what else should be included in the IBM proposal for the new ERP solution?()
第9题:
A customer has two data centers, 500 kilometers apart. The customer requests a proposal for new storage subsystems and a disaster recovery solution that provides consistent data in the event of a disaster at the local site. Which IBM System Storage DS8000 solution should the storage specialist propose to the client()
第10题:
A customer needs to share large files across three Power Systems servers to create and validate complex automotive designs. What IBM solution should be recommended?()