()is a type of bar chart that il

题目

()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

  • A、gantt chart
  • B、project histogram
  • C、milestone chart
  • D、project flowchart
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

An acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chart

A . When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process

B . When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.

C . When a process is subject to constant but stable tool wear.

D . A and B.

E . A and C


正确答案:E

第2题:

● As a control tool, the bar chart (Gantt) methods is most beneficial for:

A rearranging conflicting tasks

B depicting actual versus planned tasks

C showing the outer dependencies of tasks

D A and C.

E A and D


正确答案:B

第3题:

As a control tool, the bar chart (Gantt) methods is most beneficial for:

A.rearranging conflicting tasks

B.depicting actual versus planned tasks

C.showing the outer dependencies of tasks

D.A and C.

E.A and D


正确答案:B
B

第4题:

项目进度计划的编制,包括项目进度安排、施工组织等,通常用( )表示。

A.工艺流程图 B.逻辑框架图(LFA)

C.线条图(BAr ChArt)

D.双曲线图


正确答案:C
点评:项目进度计划是为了确定项目实施的具体时间进度安排,并分析对工艺技术及财务的影响,以保证项目的顺利实施。通常用线条图(BAr ChArt)来编制项目进度计划。详见教材P62.

考试要点:项目进度计划的编制方法。

第5题:

A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

A.gantt chart

B.project histogram

C.milestone chart

D.project flowchart


正确答案:A

第6题:

30 As a control tool, the bar chart (Gantt) methods is most beneficial for:

A. rearranging conflicting tasks

B. depicting actual versus planned tasks

C. showing the outer dependencies of tasks

D. A and C.

E. A and D


正确答案:B

第7题:

During a password recovery, what is the next step after configuring the system to boot into single- user mode?()

A. Reset the root password.

B. Press the space bar.

C. Type recovery.

D. Press the "Enter" key.


参考答案:C

第8题:

The major disadvantage of a bar chart is:

A.Lack of time-phasing.

B.Cannot be related to calendar dates.

C.does not show activity interrelationships.

D.Cannot be related to manpower planning.

E.Cannot be related to cost estimates.


正确答案:C
C

第9题:

A__(74)__is a type of bar chart that illustrates a project schedul

A.It illustrates the start and finish dates of the terminal elements and summary elements of a project.

B.Gantt chart

C.project histogram

D.milestone chart

E.project flowchart


正确答案:A
甘特图是一种用来描述项目计划的条形图,它描述了项目的各个底层工作单元以及概括性工作单元的开始日期与结束日期。

第10题:

在GSM LINE CHART窗口配置中,在style窗口选择Bar,则窗口显示的参数形状为()

A.线性图

B.柱状图

C.圆形图

D.椭圆图


参考答案:B

更多相关问题