Your Exchange Server 2010 organization contains two Hub Transport servers in a single site. The organization receives all e-mail sent to a SMTP domain named contoso.com. Your company purchases another company that uses a SMTP domain named fabrikam.com. You plan to manage message hygiene for both SMTP domains.  You need to recommend changes to the organization to support the planned deployment.  The solution must prevent e-mail sent to fabrikam.com from being delivered to your internal organization.  What should you recommend?()

  • A、Deploy a new Hub Transport server, and then create remote domains.
  • B、Deploy a new Hub Transport server, and then configure transport rules.
  • C、Deploy an Edge Transport server, and then create accepted domains.
  • D、Deploy an Edge Transport server, and then configure a federation trust.
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

You work as the enterprise exchange administrator at TestKing.com. TestKing.com makes use of Microsoft Exchange Server messaging solution. The TestKing.com network consists of a single ActiveDirectory domain named testking.com. TestKing.com is configured to run an exchange 2010 environment.  You are planning to design the installation of numerous Mailbox servers. TestKing.com Service LevelAgreement (SLA) requires the following: * The servers need to support 1,500 concurrent connections to mailboxes.* The servers need to maintain a latency of less than 20 milliseconds. You ensure deployment success you need to ensure that your design comply with the Service LevelAgreement (SLA) of TestKing.com. What should you do?()

  • A、The best option is to use the Exchange Server User Monitor (ExMon) tool to check if your design meets the requirements.
  • B、The best option is to use the Exchange Server Load Generator (LoadGen) 2010 tool to check if your design meets the requirements.
  • C、The best option is to use the Exchange Server Connectivity Analyzer (ExRCA) tool to check if your design meets the requirements.
  • D、The best option is to use the Exchange Server Jetstress 2010 tool to check if you design meets there quirements.

正确答案:B

第2题:

Your network contains two Exchange Server 2010 Edge Transport servers and five Exchange Server2010 Hub Transport servers.  All e-mail sent from your organization to the Internet is transferred by the Edge Transport servers. You need to recommend a security solution for the organization to meet the following requirements: .Ensure that users can send encrypted messages to any other organization on the Internet  .Ensure that all Exchange-related communication between Hub Transport servers and Edge Transport servers is encrypted What should you recommend?()

  • A、Deploy IPsec.
  • B、Deploy SMTP over SSL.
  • C、Implement Domain Security.
  • D、Implement Secure/Multipurpose Internet Mail Extensions (S/MIME).

正确答案:D

第3题:

Your vessel is crossing a narrow channel.A vessel to port is within the channel and crossing your course.She is showing a black cylinder.What is your responsibility ________.

A.Hold your course and speed

B.Sound the danger signal

C.Begin an exchange of passing signals

D.Do not cross the channel if you might impede the other vessel


正确答案:D

第4题:

You have an Exchange Server 2010 organization. You design a deployment of multiple Mailbox servers.  Your companys Service Level Agreement (SLA) states that servers must support 1,000 concurrent connections to mailboxes while maintaining an RPC latency of less than 20 milliseconds.  You need to verify that your design meets the requirements of the SLA before you deploy servers in the production environment.  Which tool should you use?()

  • A、Exchange Server Jetstress 2010
  • B、Exchange Server User Monitor (ExMon)
  • C、Exchange Server Load Generator (LoadGen) 2010
  • D、Exchange Server Remote Connectivity Analyzer (ExRCA)

正确答案:C

第5题:

Your company has a main office and 10 branch offices. You have an Exchange Server 2010 organization.  All Exchange servers are installed on virtual machines.  You need to create a monitoring plan for the Exchange servers that meets the following requirements:.Identify Exchange server errors .Provide alerts when Exchange services are stopped .Produce statistical analysis and reporting Which tool should you include in the plan?()

  • A、Microsoft System Center Service Manager
  • B、Microsoft System Center Operations Manager
  • C、Microsoft System Center Configuration Manager
  • D、Microsoft System Center Virtual Machine Manager

正确答案:B

第6题:

Your network contains an Exchange Server 2010 server.You need to prevent a user named User1 from downloading attachments larger than 50 KB when using Exchange ActiveSync.Your solution must not affect other users.  What should you do first?()

  • A、Modify User1 Mailbox properties
  • B、Create a New ActiveSync Mailbox Policy
  • C、Create a New Exchange ActiveSync Mailbox policy
  • D、Modify properties of Default Exchange ActiveSync Mailbox policy

正确答案:C

第7题:

Company.com has employed you as their Exchange administrator.The Company.com network contains Mailbox servers that are configured to run either Exchange Server 2007 or Exchange Server 2010.During the course of the week you receive an instruction from the CIO to ensure that all e-mail messages stored for more than 90 days in the Inbox folder of clients be deleted. What should you do?()

  • A、Your best option would be to create a new retention policy.
  • B、Your best option would be to create a new message classification.
  • C、Your best option would be to create new managed content settings.
  • D、Your best option would be to create a new managed custom folder.

正确答案:C

第8题:

You work as the exchange administrator at TestKing.com. The TestKing.com network contains an Exchange Server 2010 Organization. You are responsible for managing the Exchange network for TestKing.com The organization contains three Exchange Server 2010 Edge Transport Servers and seven ExchangeServer 2010 Hub Transport servers. The Edge Transport server is used to transfer e-mail from your organization to the Internet. During the course of day you receive an instruction form the CIO to ensure that all clients is able to send encrypted messages to other organizations over the Internet as well asensuring that communications between the Hub Transport servers and the Edge Transport servers isencrypted. What should you do?()

  • A、Your best option would be to deploy SMTP over SSL.
  • B、Your best option would be to implement Security/Multipurpose Internet Mail Extensions (S/MINE).
  • C、Your best option would be to deploy IPsec.
  • D、Your best option would be to implement Domain Securtiy.

正确答案:B

第9题:

You are the Exchange administrator for your organization.You need to move a user’s mailbox from the mailbox server role of an Exchange 2007 SP2 server to the mailbox server role of an Exchange 2010 server in the same forest.You must ensure that the end-user can still access their e-mail account.What action should you take?()

  • A、Run the Move-Mailbox cmdlet
  • B、Run the New-MoveRequest cmdlet
  • C、Use the Exchange Management console to issue a New Remote Move Request
  • D、Run the Set-MailboxDatabaseCopy cmdlet

正确答案:B

第10题:

Explanation/Reference: QUESTION 29 You have an Exchange Server 2010 organization named contoso.com.  Your company plans to provide business continuity services for a company named Fabrikam. Fabrikam has an Exchange Server 2007 organization and uses the fabrikam.com SMTP domain. You need to configure your organization to queue and relay all e-mail messages sent to fabrikam.comfrom the Internet.  What should you do?()

  • A、Create a new remote domain, and then modify the mail exchange (MX) record for the fabrikam.com public DNS domain.
  • B、Create a new remote domain, and then modify the mail exchange (MX) records for the contoso.com public DNS domain.
  • C、Create a new External Relay Accepted Domain, and then modify the mail exchange (MX) records for the contoso.com public DNS domain.
  • D、Create a new External Relay Accepted Domain, and then modify the mail exchange (MX) records for the fabrikam.com public DNS domain.

正确答案:D