Which element, defined as a child of a
第1题:
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.
第2题:
Which of the following is an element of procurement management:
A inspection
B purchasing
C estimating
D expediting
E A, B and D only
第3题:
Which of the following networking methods allows us to show that the last % of one element cannot be completed until % of a previous element has been completed?
A.PERT
B.ADM
C.PDM
D.All of the above.
E.A and C only.
第4题:
94 Which is not an element of procurement management?
A. Purchasing
B. Expenditure
C. Marketing
D. Inspection
E. B and D
第5题:
Which of the following is an element of procurement management:
A. inspection
B. purchasing
C. estimating
D. expediting
E. A, B and D only
第6题:
Which is not an element of procurement management?
A Purchasing
B Expenditure
C Marketing
D Inspection
E B and D
第7题:
132 Which of the following is an element of procurement management:
A. inspection
B. purchasing
C. estimating
D. expediting
E. A, B and D only
第8题:
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A . Element P
B . Element Q
C . Element R
D . Element S
E . None of the above.
第9题:
161 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?
A. PERT
B. ADM
C. PDM
D. All of the above.
E. A and C only
第10题:
43 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?
A. PERT
B. ADM
C. PDM
D. All of the above.
E. A and C only.