102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A. Element PB. Element QC. Element RD. Element SE. None of the above

题目

102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

A. Element P

B. Element Q

C. Element R

D. Element S

E. None of the above

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.

A . Over, 16.66

B . Under, 16.66

C . Over, 10.0

D . Under, 10.0

E . None of the above.


正确答案:A

第2题:

Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

A . 0.875

B . 1.14

C . 0.952

D . 0.833

E . 1.2


正确答案:B

第3题:

Which of the following networking methods allows us to show that the last % of one element cannot be completed until % of a previous element has been completed?

A.PERT

B.ADM

C.PDM

D.All of the above.

E.A and C only.


正确答案:C
C

第4题:

161 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?

A. PERT

B. ADM

C. PDM

D. All of the above.

E. A and C only


正确答案:C

第5题:

Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

A . Element P

B . Element Q

C . Element R

D . Element S

E None of the above.


正确答案:D

第6题:

Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

A . 1.1

B . 0.9

C . 0.956

D . 1.15

E . 0.869


正确答案:A

第7题:

Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

A . Element P

B . Element Q

C . Element R

D . Element S

E . None of the above.


正确答案:C

第8题:

Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

A . Become worse, become worse

B . Become worse, improved

C . Improved, increased

D . Improved, become worse

E . None of the above are correct


正确答案:E

第9题:

Using the situation stated in the Special window, what is the cost performance index for Case #9?

A . 1.1

B . 1.91

C . 0.83

D . 1.2

E . None of the above


正确答案:A

第10题:

43 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?

A. PERT

B. ADM

C. PDM

D. All of the above.

E. A and C only.


正确答案:C

更多相关问题