题目

The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()

  • A、Evaluate phase exit milestones using sufficiency criteria
  • B、Flexible entry and exit criteria to minimize schedule delays
  • C、Quality measures reported only to the project steering committee
  • D、Many work teams with few members to maximize the number of deliverable hand-offs
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The project life-cycle can be described as:

A.project concept, project planning, project execution, and project close-out.

B.project planning, work authorization, and project reporting.

C.project planning, project control, project definition, WBS development, and project termination.

D.project concept, project execution, and project reporting.

E.All of the above.


正确答案:A
A

第2题:

167 The project life-cycle can be described as:

A. project concept, project planning, project execution, and project close-out.

B. project planning, work authorization, and project reporting.

C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

E. All of the above


正确答案:A

第3题:

The project charter is a document designed to tell _____ exactly what the project entails.

AThe project manager

BThe project office

CThe project team

DThe project sponsor

EAnyone associated with the project


正确答案:E

 

第4题:

● The scope baseline/project charter is prepared by the:

A Project manager

B Project manager and project office

C Project manager, project office and functional team

D Project manager, project office, functional team and project sponsor

E Project manager, project sponsor and customer/user


正确答案:E

第5题:

139 The project charter is a document designed to tell _____ exactly what the project entails.

A. The project manager

B. The project office

C. The project team

D. The project sponsor

E. Anyone associated with the project


正确答案:E

第6题:

The quality objectives are approved in the conceptual stage of the project by the:

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner


正确答案:E

第7题:

123 The scope baseline/project charter is prepared by the:

A. Project manager

B. Project manager and project office

C. Project manager, project office and functional team

D. Project manager, project office, functional team and project sponsor

E. Project manager, project sponsor and customer/user


正确答案:E

第8题:

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user


正确答案:E
E

第9题:

● Interfacing with the customer after project go-ahead is the responsibility of:

A Project sponsor

B Project team

C Project manager

D Functional manager

E All of the above are possible, based upon the size and complexity of the project


正确答案:C

第10题:

● (74) is primarily concerned with defining and controlling what is and is not included in the project.

(74)

A. Project Time Management

B. Project Cost Management

C. Project Scope management

D. Project Communications Management


正确答案:C