Risks other()All Risks and War Risk can be covered if the extra pr- enium should be borne by the buyer.

题目

Risks other()All Risks and War Risk can be covered if the extra pr- enium should be borne by the buyer.

参考答案和解析
正确答案:than
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第2题:

77 Since risk is associated with most projects, the best course of action is to:

A. cover all project risks by buying appropriate insurance

B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C. avoid projects with clear and present risks

D. eliminate all known risks prior to the execution phase of the project

E. identify various risks and implement actions to mitigate their potential impact


正确答案:E

第3题:

Project Risk Management is based on which of the following premises:

A the future is unknown.

B unknowns can result in risks or opportunities.

C we cannot control risk events.

D project risk impact can be measured and controlled

E All of the above.


正确答案:E

第4题:

-But in your case, we strongly recommend War Risks and WPA. - ________

A OK, then please cover both War Risks and WPA for us. ;

B Well, that rate is acceptable. Thanks. ;

C But the extra premium is for buyer’s account.


参考答案:A

第5题:

108 Project Risk Management is based on which of the following premises:

A. the future is unknown.

B. unknowns can result in risks or opportunities.

C. we cannot control risk events.

D. project risk impact can be measured and controlled

E. All of the above


正确答案:E

第6题:

Since risk is associated with most projects, the best course of action is to:

A cover all project risks by buying appropriate insurance

B ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C avoid projects with clear and present risks

D eliminate all known risks prior to the execution phase of the project

E identify various risks and implement actions to mitigate their potential impact


正确答案:E

第7题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第8题:

Risks that cannot be identified or evaluated _____ .

A should be deflected to the contracting officer.

B should be handled via contingency allowances.

C should be ignored, since they cannot be identified.

D should be ignored, since they are not covered in the Risk Assessment.

E C and D


正确答案:B

第9题:

145 Risks that cannot be identified or evaluated _____ .

A. should be deflected to the contracting officer.

B. should be handled via contingency allowances.

C. should be ignored, since they cannot be identified.

D. should be ignored, since they are not covered in the Risk Assessment.

E. C and D


正确答案:B

第10题:

听力原文:M: Can you give an example of types of risks Banks face?

W: Yes. The major type of risks is called credit risk. It means a counterpart fails to perform. according to a contractual arrangement.

Q: What are they talking about?

(13)

A.A contractual arrangement.

B.A counterpart.

C.Many types of risks.

D.Credit risk.


正确答案:D
解析:他们在谈论银行所面临的风险,女士说“The major type of risks is called credit risk.”,所以D选项符合题意。

更多相关问题