Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failure
Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occurs
Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHA
Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover
第1题:
A customer has provided the pSeries technical specialist with details of an HACMP solution that they would like validated. The solution is for two POWER4+ p630 servers directly attached to a FAStT600 storage server as the shared storage. Each system has the following: ? 2 integrated network ports ? 2 fibre channel adapter cards ? 1 power supply and redundant cooling ? HACMP v5.1 In addition to a second power supply, what further requirements, if any, are needed to validate this solution and ensure no single point of failure? ()
第2题:
A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used. Which of the following fulfills the customer requirements?()
第3题:
A customer has many RS/6000s and POWER4 systems running different AIX applications. What should the customer do to best position themselves for the migration to POWER5?()
第4题:
A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?()
第5题:
A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them. Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()
第6题:
A customer has ordered a rack, a p650, two p630s, and two p615s. During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit. However, the specialist knows that the p650 will be racked, but the other systems will arrive separately. In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()
第7题:
A customer wants to expand their current storage environment, but has floor space for only two machine frames or two racks. Their environment consists of IBM SAN Volume Controllers and IBM DS4000 systems. The DS4000 systems are at end of lease. The customer wants the maximum number of disks possible in two frames. Which of the following solutions is best for this customer?()
第8题:
A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server. What is the minimum PowerVM edition that supports the customer requirement?()
第9题:
A customer has a requirement for a single AIX LPAR to be highly available. The customer only has enough funding to purchase a single system. Which would be the most critical option to mitigate AIX availability?()
第10题:
A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()