单选题When ordering a new IBM Power Systems server, a customer is given the option of two types of Hardware Management Console:7042-CR4 and 7042-C06. Which main difference between the options would influence the customer's decision?()A The 7042-CR4 is a rack

题目
单选题
When ordering a new IBM Power Systems server, a customer is given the option of two types of Hardware Management Console:7042-CR4 and 7042-C06. Which main difference between the options would influence the customer's decision?()
A

The 7042-CR4 is a rack mounted model, compared to the 7042-C06, which is adesktop.

B

The 7042-CR4 is limited to 16 managed systems, compared to a limit of 32 for the 7042-C06.

C

The 7042-C06 has faster CPUs and twice the RAM compared to the 7042-CR4,which is suited to large enterprise deployments.

D

The 7042-C06 can manage POWER5-based hardware, in addition to POWER6, while the 7042-CR4 can only manage POWER6-based hardware.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A sales specialist is presented with a very large, complex opportunity. The customer is in the process of identifying business requirements.  Which of the following tasks is most important to position IBM as the leader to capture this opportunity?()

  • A、Call the IBM Client Representative and ask the rep to influence the company’s executives.
  • B、Develop a strategy to better understand and possibly influence the customer’s success criteria.
  • C、Using IBM’s opportunity management system, request a technical team be formed to design a solution.
  • D、Nominate the customer for a funded IBM Server Consolidation study.

正确答案:B

第2题:

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

  • A、p5 hardware, AIX 5.2, Virtual I/O Server
  • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
  • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
  • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

正确答案:C

第3题:

When ordering a new IBM Power Systems server, a customer is given the option of two types of Hardware Management Console:7042-CR4 and 7042-C06.Which main difference between the options would influence the customer‘s decision?()

A.The 7042-CR4 is a rack mounted model, compared to the 7042-C06, which is adesktop.

B.The 7042-CR4 is limited to 16 managed systems, compared to a limit of 32 for the 7042-C06.

C.The 7042-C06 has faster CPUs and twice the RAM compared to the 7042-CR4,which is suited to large enterprise deployments.

D.The 7042-C06 can manage POWER5-based hardware, in addition to POWER6, while the 7042-CR4 can only manage POWER6-based hardware.


参考答案:C

第4题:

A customer has 12 x445s and 20 x365s in their datacenter that are dedicated to production workloads.  The customer wants to standardize on IBM Director as their Intel environment systems management platform.  Which server platform is supported as a Director server?()

  • A、zSeries
  • B、pSeries
  • C、iSeries
  • D、iSeries with IXA Adapter

正确答案:C

第5题:

A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers.  Which of the following should the Sales Specialist emphasize to address the pricing difference?()

  • A、Higher rack density that reduces data center footprints
  • B、Internal upgrades that only IBM can offer
  • C、Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches 
  • D、The Rear Door Heat eXchanger that only IBM can offer

正确答案:C

第6题:

You have successfully sold and installed your customer’s System x solution. Sometimes, the overall succeed of a sale depends on how well you have trained your customer to support their new hardware. Please consider the following tools. Which one would be the best for protectively determining a server outage, and contacting the system administrator about the outage?()

  • A、CDAT
  • B、Configuration and Options Guide (COG)
  • C、Physical Alarm Sounding in Data Center
  • D、IBM Systems Director

正确答案:D

第7题:

A customer is looking for a new file and print server and is considering a 2-socket Intel server with redundant power and hard disk that must fit in the current server rack. With 2U available in the rack, the customer is looking for the best price performance ratio.  Which IBM server will fit the best for this customer?()

  • A、x3200
  • B、x3455
  • C、x3550
  • D、x3650

正确答案:C

第8题:

A customer has ordered a rack, a p650, two p630s, and two p615s.  During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit.  However, the specialist knows that the p650 will be racked, but the other systems will arrive separately.  In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()

  • A、Because additional systems would require more power receptacles
  • B、Because the customer may need to do additional facilities planning
  • C、Because the customer needs additional funding to cover the services
  • D、Because postponing the eventual discussion will likely lead to customer dissatisfaction

正确答案:D

第9题:

A customer has 15 IBM x365 servers in a rack environment and is using IBM Director for systems management.  They require the ability to restart any server independent of the operating system.  Which of the following is the most cost-effective solution?()

  • A、Interconnect the service processors and use the IBM Director Agent
  • B、Install RSA II in each server and chain together the systems management processors
  • C、Install the RSA II in the top server and chain together the service processor interconnect
  • D、Install the IBM Director Agent on each server and use the remote control function to restart the servers

正确答案:C

第10题:

A customer has a large HP Intel infrastructure and is actively managing these servers with Insight Manager.  They recently purchased an IBM x346 server for a remote office database project.  They do not want to run additional systems management software but require to be notified of PFA and hardware alerting on critical hardware components.  Which of the following solutions would accomplish this?()

  • A、Install an RSA II Slimline card on the IBM server and configure to send email alerts
  • B、Enable the IBM management option in Insight Manager
  • C、Install and configure a Director agent on the IBM server
  • D、Configure the systems management processor on the IBM server

正确答案:A