A customer is adding a new p5 machine to their environment. 

题目
单选题
A customer is adding a new p5 machine to their environment.  The machine will host several DB2 partitions running AIX 5.2.  They currently have two SAN directors and an IBM ESS.  The SAN design allows for concurrent maintenance.  What is required on each partition to attach to the SAN?()
A

A minimum of two HBAs; the customer will need to download SDD

B

A minimum of four HBAs; the customer will need to download SDD

C

A minimum of two HBAs; the customer will need to configure MPIO

D

A minimum of four HBAs; the customer will need to configure MPIO

参考答案和解析
正确答案: A
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Companycom has just added some new disk drives to a p5 590. The customer needs to know the largest Logical Track Group that these drives will support. What is the best way to locate this information?()

  • A、Use lquerypv to read the drive
  • B、Use lspv and look at PP Size value
  • C、Look on the outside of the drive itself
  • D、Use bootinfo to find the LTG on the drive

正确答案:A

第2题:

Machine policy templates can be assigned based on certain attributes of a machine. A customer  organizes their machines based on the following requirements:   The machines are all placed in specific Organizational Units in the Active Directory.   The customer has Citrix Servers, and they have a specific naming convention meant only for their Citrix Servers. The customer has DHCP enabled for all the client machines.   The customer has made it clear that they should not need to change anything in the existing infrastructure. Given these requirements, which single assignment attribute would be chosen for assigning machine policy templates?()

  • A、Hostnames
  • B、IP Addresses
  • C、Machine Group Tag
  • D、Active Directory Groups

正确答案:C

第3题:

Companycom is buying an application solution that bases its software licensing on the number of CPUs per machine. They will be running two instances of this application and will require 8 CPUs each. A second application is priced based on CPUs per LPAR as well as the class of machine. That application will require 8 CPUs. What is the best hardware to propose to keep the software cost low?()

  • A、A 24 way p5 595 with 3 LPARs
  • B、A 24 way p5 595 with 2 LPARs
  • C、One p5 570s 16 way and one p5 570 8 way
  • D、One p5 595 12 way active and 12 way inactive, and one p5 570 8 way

正确答案:C

第4题:

A customer wants to purchase an IBM System Storage DS8700 to support a high-performance database environment.  Which technical solution gives the customer the best relationship between I/O performance at the machine’s backend vs. capacity installed in the machine()

  • A、additional installation of the first and second expansion frame will increase the backend performance capability
  • B、the usage of 300 GB/15k FC disks will give the server a high-performance backend capability
  • C、performance Accelerator restricts the number of disks connected to one device adapter pair to 32 disks
  • D、the second RIO-G loop between the base frame and the first expansion increases the backend performance

正确答案:C

第5题:

A customer needs detailed information on the internal architecture of the new p5-570.  Which of the following is the most appropriate place to get this documentation?()

  • A、IBM sales manual
  • B、IBM Redbooks Website
  • C、IBM eServer p5 and pSeries Qs and As
  • D、IBM eServer p5 and pSeries Facts and Features

正确答案:B

第6题:

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

  • A、p5 hardware, AIX 5.2, Virtual I/O Server
  • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
  • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
  • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

正确答案:C

第7题:

Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()

  • A、Free up one HMC and update the software for use with the p5 570
  • B、Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC
  • C、Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570
  • D、Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software

正确答案:A

第8题:

An existing IBM customer has some iSeries servers in their environment.  The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications.  The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms.  Which of the following will accomplish this?()

  • A、Share the data over the Ethernet LAN.
  • B、Install the IXA Adapter in the iSeries server.
  • C、Install the IXA Adapter in the xSeries server.
  • D、Attach both servers to an IXS switch.

正确答案:C

第9题:

The account executive is asking about post-sales support for a new p5 HMC.  They need the pSeries technical specialist to configure an HMC with software support for the customer.  Which of the following should the specialist include in the configuration?()

  • A、Supportline
  • B、ServiceSuite
  • C、Software Maintenance Agreement (SWMA)
  • D、Machine Control Program Remote Support Agreement (MCPRSA)

正确答案:D

第10题:

Companycom purchased a p5 570 with no plans to partition. The customer plans to use the ASMI interface to power on and off the machine. How can ASMI be accessed without a HMC?()

  • A、By typing diags and then going to the ASMI menus
  • B、Through SSH from a TCP/IP connection on the server
  • C、Through WebSM which is connected to a system Ethernet port
  • D、By connecting through a web browser to an HMC Ethernet port

正确答案:D