Company.com has four pSeries servers in their data center an

题目
单选题
Company.com has four pSeries servers in their data center and wants to deploy multiple Micro-Partitions.  Which of the following data center servers can be used for this purpose?()
A

p5-520 running Virtual I/O Server

B

p690 running AIX 5L V5.3

C

p5-510 running AIX 5L V5.2

D

p5-520 running two dedicated processor partitions

参考答案和解析
正确答案: D
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A small business currently has four separate servers, three of which perform low-overhead tasks with small memory footprints. How could the company BEST reduce power consumption among these four servers, while not sacrificing functionality?()

  • A、Enable each server’s Cool ’n’ Quiet and/or SpeedStep functionality so that processing power is conserved.
  • B、Enforce auto-shutdown routines on all four servers for after-hours power saving while the office is closed.
  • C、Consolidate the four servers onto the best two,combining them logically by tasks and memory consumption.
  • D、Consolidate the four servers onto the most powerful machine using virtualization.

正确答案:D

第2题:

A network design shows that R1 has four different possible paths from itself to the Data Center subnets. Which one of the following commands is most likely to show you all the possible next - hop IP addresses for these four possible routes?()

  • A、show ip eigrp topology
  • B、show ip eigrp topology all - links
  • C、show ip route eigrp
  • D、show ip route eigrp all - links
  • E、show ip eigrp topology all - learned

正确答案:B

第3题:

Certkiller .com has a remote data center with servers connected to a local datacenter through a high-speed network. Which of the following methods is the most convenient to use to install and upgrade the servers in the remote center using locally managed install images?()

A.NIM

B.HAGEO/HACMP

C.NFS

D.ftp, rsh and rexec


参考答案:A

第4题:

A customer has two locations that host their pSeries servers.  Traffic is being routed through the public Internet.  The customer needs to exchange confidential financial data between the servers.  Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()

  • A、A DCE domain
  • B、A Kerberos domain
  • C、A PPP tunnel between the servers
  • D、An IPSEC tunnel between the servers

正确答案:D

第5题:

Company.com has installed and configured a VIO server utilizing a Shared Ethernet Adapter and is investigating some network performance issues visible on the clients. The customer wants to understand the total network connectivity from the clients out to the data center routers.  Which of the following commands will identify the Shared Ethernet Adapter mapping?()

  • A、ifconfig -a
  • B、netstat -nr
  • C、lsmap -all -net
  • D、lsdev -Cc adapter

正确答案:C

第6题:

The current data center has run out of space. A room that is located next to the existing data center is then used to house two racks containing six servers. Six months later, physical housekeeping is performed as part of a mid-year maintenance plan. Which environmental condition discovered in the room is LEAST critical?()

  • A、 There are discolored ceiling tiles near the middle of the room.
  • B、 Large amounts of dust have accumulated in the corners of the room.
  • C、 The anti-static carpet has been removed resulting in a bare painted concrete floor.
  • D、 A wet pipe water-based sprinkler system has been installed above the racks.

正确答案:C

第7题:

An SNMP alert has been generated by a server in the main data center.The alert stated that the internal temperature of the server has exceeded the threshold.No other servers in the rack have experienced problems,and no other alerts have come from that server about any other events.Which of the following is the cause of this issue?()

  • A、Rack cooling equipment failure
  • B、Dust collection in the server
  • C、Server processor failure
  • D、Server power supply failure

正确答案:B

第8题:

A manufacturing customer has liminted space remaining in their data center and is concerned about rising power costs. The customer applications require very large amounts of memory. They want server redundancy and no downtime. Which of the following architectural features should be discussed with them?()

  • A、iDataPlex with vSphere
  • B、Four x3550 M3 servers,vSphere and racks
  • C、BladeCenter, HX5 blades and vSphere
  • D、One x3950 X5 servers andvSphere

正确答案:C

第9题:

Company.com has four pSeries servers in their data center and wants to deploy multiple Micro-Partitions.  Which of the following data center servers can be used for this purpose?()

  • A、p5-520 running Virtual I/O Server
  • B、p690 running AIX 5L V5.3
  • C、p5-510 running AIX 5L V5.2
  • D、p5-520 running two dedicated processor partitions

正确答案:A

第10题:

A customer is getting ready to install a new pSeries system into their data center.  They are concerned about providing the appropriate clearance around their 7014-T42 to allow for maintenance.  What reference material should the pSeries technical specialist provide to the customer?()

  • A、Sales Manual
  • B、Announcement Letter
  • C、Site and Hardware Planning Information
  • D、Adapter, Devices, and Cable Information for Multiple Bus Systems

正确答案:C