第1题:
Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
第2题:
113 Screening of risk events for potential risk is known as _____ .
A. problem structuring.
B. risk identification
C. risk quantification
D. risk modeling
E. risk mitigation
第3题:
● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
.Risk Monitoring and Control
第4题:
Workarounds are determined during which risk management process? (75).
A. Risk identification
B. Quantitative risk analysis
C. Plan risk responses
D. Risk monitoring and control
第5题:
危险度包括系统内的现实危险度和系统外的现实危险度,其中系统外的现实危险度又包括固有危险度和可控危险度。( )
此题为判断题(对,错)。
第6题:
196 Giving a part of project work to a contractor is an example of:
A. risk mitigation
B. risk assignment
C. risk delegation
D. risk deflection
E. risk assumption
第7题:
危险源存在的危险严重度的乘积称为危险度。危险度包括系统内的现实危险度和系统外的现实危险度,其中,( )又包括固有危险度和可控危险度。
第8题:
Screening of risk events for potential risk is known as _____ .
A problem structuring.
B risk identification
C risk quantification
D risk modeling
E risk mitigation
第9题:
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
第10题:
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management